Free Motion to Amend Pleadings - Rule 15 - District Court of Federal Claims - federal


File Size: 62.1 kB
Pages: 14
Date: July 10, 2008
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 3,334 Words, 20,940 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/22730/15-2.pdf

Download Motion to Amend Pleadings - Rule 15 - District Court of Federal Claims ( 62.1 kB)


Preview Motion to Amend Pleadings - Rule 15 - District Court of Federal Claims
Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 1 of 14

EXHIBIT 1

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 2 of 14

IN THE UNITED STATES COURT OF FEDERAL CLAIMS WHITE BUFFALO CONSTRUCTION, INC., an Oregon corporation, Plaintiff, v. (Contract Disputes Act) UNITED STATES OF AMERICA, by and through the Department of Transportation, Federal Highway Administration, Western Federal Lands Division, Defendant. Trial Date: August 4, 2008 Pretrial Conference: July 28, 2008 Electronically Filed July 10, 2008 PARTIES 1. White Buffalo Construction, Inc. ("White Buffalo") is an Oregon corporation in No. 99-961C (Consolidated with Case Nos. 07-738C and 00-415C) Senior Judge Loren A. Smith AMENDED COMPLAINT Federal Highway Administration Contract No. DTFH70-98-C-00027

good standing and duly licensed as a contractor. 2. The defendant is the United States of America, acting by and though the

Department of Transportation, Federal Highway Administration, Western Federal Lands Highway Division ("FHA"). JURISDICTION 3. This Court has jurisdiction of the claims presented here under the Contract

Disputes Act of 1978 (the "CDA"), 41 U.S.C. § 609(a)(1), and 28 U.S.C. § 1491(a)(2). STATEMENT OF FACTS 4. On August 20, 1998, the United States awarded to White Buffalo FHA Contract

No. DTFH70-98-C-00027 (the "Contract") on the Siskiyou National Forest ("SNF").

1
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 3 of 14

5.

At all material times herein, White Buffalo performed all obligations on its part to

be performed or was otherwise excused from performance as herein alleged. White Buffalo was ready, willing and able to perform all remaining obligations. 6. FHA failed to cooperate with White Buffalo by not allowing White Buffalo to

commence work until September 15, 1998 and by not providing the required additional contract time due to White Buffalo because of the late Notice to Proceed ("NTP"). FHA erred in its belief that White Buffalo could not commence work on September 1, 1998 due to environmental restrictions. 7. The contract contains environmental restrictions that prohibit commencement of

work until September 15, 1998 for four of the ten sites on FDR 33 because clearing and grubbing was required at these sites. However, work could have started September 1, 1998 on six of the sites on FDR 33, but FHA did not allow this. The contract allowed work to be performed without any restriction at Mile Post ("MP") 46.2. 8. Due to the failure of FHA to issue the NTP on September 1, 1998, White Buffalo

lost 25 percent of its work window for "wetted perimeter" work at MP 46.2. 9. FHA concealed from White Buffalo the fact that it had discovered "excess"

material that it had directed White Buffalo to remove from MP 46.2 was actually needed at that site to complete the fill as shown in the drawings and as previously argued by White Buffalo. 10. FHA concealed from White Buffalo that it had decided not to seek any extension

from the permitting agencies to work in the "wetted perimeter." FHA misled White Buffalo by informing it that the permitting agencies had refused to grant any extension. When White Buffalo directly approached the permitting agencies and obtained permission from them to continue work, FHA refused to allow White Buffalo to continue any installation and, instead,

2
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 4 of 14

directed White Buffalo to perform only winterization work and stopped all work at the culvert at MP 46.2 11. FHA unnecessarily restricted White Buffalo's operations by using the term

"wetted perimeter" and defining areas within the "wetted perimeter" as any area that it arbitrarily determined could be reached by high water. FHA used the unusual term "wetted perimeter of any stream" to indicate areas that would be subject to the restrictions of the permit even though the permit and the permitting agencies use the term "in-water work." 12. FHA restricted White Buffalo's operations in any area that it arbitrarily

determined could be reached by high water. In the case of the critical repair at MP 46.2, White Buffalo was prohibited after November 1, 1998 from working on installations in areas that were clearly well out of the stream, including working on the fill at the top of the culvert. 13. 14. FHA later changed the term "in-water work" in 1999 for the completion contract. FHA refused to address the changed condition at FDR 33 MP 46.7. This failure

to act resulted in White Buffalo's incurring delays and additional costs due to the unstable overburden at the rock cut at MP 46.7. Multiple failures of the overburden at this site occurred after the first shot, when the changed condition was evident. This significantly impeded the course and prosecution of the work and increased the costs to White Buffalo. 15. On or about November 3, 1998, White Buffalo met with Contracting Officer

William Parsons ("CO Parsons") and other FHA officials in Vancouver at the request of White Buffalo to discuss concerns that White Buffalo had about lack of progress and its belief that it was being hindered from completing the project. 16. On or about November 13, 1998, Contracting Officer Carol H. Jacoby

("CO Jacoby") issued a cure notice.

3
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 5 of 14

17.

On or about December 1, 1998, CO Parsons issued a final decision notifying

White Buffalo that it was terminated, effective upon White Buffalo's receipt of the notice (December 3, 1998), alleging that White Buffalo was in default. 18. On or about December 3, 1998, FHA required White Buffalo, through its surety,

Insurance Company of the West ("ICW"), to retain another contractor to perform what was characterized as emergency work. White Buffalo and ICW retained Kerr Contractors ("Kerr") to perform this work. 19. As soon as White Buffalo was terminated, FHA had Kerr start removal of the

slide. Within a week, U.S. Forest Service Geologist Mickley met with FHA and determined that conditions were unsafe and ordered FHA to cease work and to prepare a redesign for the site at MP 46.7. 20. FHA told White Buffalo, ICW and the completion contract bidders that there

would be no changes or redesigns to the contract and that work would be completed as per the Contract. In fact, FHA had already commenced work on redesigning MP 46.7 as well as several other sites. 21. White Buffalo made repeated requests for FHA redesigns, but FHA claimed that

there were none. White Buffalo filed a Freedom of Information Act ("FOIA") action, the redesign for MP 46.7 was eventually provided and FHA paid White Buffalo's legal costs. White Buffalo discovered later in discovery that there were additional redesigns for several other sites that were not provided in the earlier FOIA request. 22. On or about December 19, 1998, FHA suspended work on the project for the

winter to redesign portions of the project as requested by SNF.

4
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 6 of 14

23.

On January 24, 1999, FHA began charging White Buffalo interim liquidated

damages of $400 per day and continued charging through October 3, 1999. 24. White Buffalo was not paid for any work it performed on the project from

September 1, 1998 until it was terminated for default on December 3, 1998. 25. On or about February 1999, ICW, under a reservation of rights, tendered

Tidewater Contractors ("TWC") as the completion contractor for the project, and FHA accepted TWC. 26. On or about May 1999, ICW was paid approximately $102,000 for work

performed by White Buffalo. FHA retained $100,000 to cover liquidated damages for the period January 24, 1999 through September 30, 1999. 27. FHA issued modifications #1-3 to TWC on May 21, 1999, which added additional

work and additional time to complete the project. 28. Under the Completion Contract, FHA relaxed specifications for TWC and sought

and obtained relaxed environmental restrictions from other agencies. Under the Completion Contract, work previously performed by White Buffalo that had been deemed unacceptable before termination was accepted by FHA without any additional work or modification by TWC. FHA also paid TWC for additional quantities of work at several sites that they did not perform. 29. 30. FHA accepted the project as complete from TWC on or about October 29, 1999. FHA opened FDR 33 to public travel on or about October 29, 1999, along with

roads FDR 3347 and FDR 3347020. 31. Liquidated damages were assessed by FHA to White Buffalo from January 24,

1999 until October 3, 1999 and were deducted from sums retained. In or about November 1999, FHA requested that ICW pay to FHA an additional $1,200 in liquidated damages.

5
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 7 of 14

32.

White Buffalo filed a complaint under the CDA in the U.S. Court of Federal

Claims appealing the Termination for Default on or about November 30, 1999. The case is captioned White Buffalo Construction, Inc. v. United States, No. 99-961-C, and is assigned to Judge Loren A. Smith. 33. On December 21, 1999, White Buffalo requested the Contracting Officer (the

"CO") to issue a final decision on the liquidated damages claims and to further set forth the legitimate reasons that liquidated damages should not be withheld and should be released to White Buffalo. 34. On or about January 6, 2000, White Buffalo received from the FHA documents

whose disclosure was compelled by a suit brought by White Buffalo under FOIA. The documents revealed that, contrary to repeated prior FHA representations, FHA had in fact redesigned the rock cut at MP 46.7. 35. On April 20, 2000, CO Parsons issued a final determination that the liquidated

damages for the interim completion date are $101,200 based on 253 days at $400 per day. 36. On or about July 14, 2000, White Buffalo filed a complaint under the CDA in the

U.S. Court of Federal Claims. Captioned White Buffalo Construction, Inc. v. United States, No. 00-415-C, this action challenges the liquidated damages award. Cases Nos. 99-961C and 00-415-C were consolidated on or about July 18, 2000. 37. In or about January 2004, FHA announced that it had decided to convert the

termination of White Buffalo from a default to a termination for the convenience of the government. FHA consequently also withdrew its claim for liquidated damages. FHA also invited from White Buffalo submission of convenience-termination settlement proposals.

6
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 8 of 14

38.

On January 13, 2005, White Buffalo timely filed with FHA its certified proposal,

incorporated by reference herein, in the amount of $1,435,733.53. This included a claim for $925,834.91 in lost profits. 39. On October 16, 2006, White Buffalo filed with FHA its revised proposal,

incorporated by reference herein, in the amount of $1,251,404.81, which then was certified on November 10, 2006. The revised proposal reduced from $925,834.91 to $870,667 the lostprofits claim. The reduction resulted from credits given to FHA of $28,183 for G&A and $26,985 for Equipment/Vehicle/Fuel, which were among unallocated costs sought elsewhere in the Revised Settlement Proposal. Of that $870,667 profit, $345,916 is for profit on work performed before termination. The $524,751 remainder is for profits lost on terminated future work and is the subject of a separate Court of Federal Claims action by White Buffalo against the United States. 40. On or about April 19, 2007, White Buffalo supplemented the Certifications for its

January 13, 2005 Settlement Proposal and its October 16, 2006 Revised Settlement Proposal (the "Supplement"), incorporated by reference herein. The Supplement did not change the amounts sought in the October 16, 2006 Revised Settlement Proposal. 41. On June 26, 2007, White Buffalo separately certified and submitted its Revised

Settlement Proposal, incorporated by reference herein. As with the April 19, 2007 Supplement and October 16, 2006 Revised Settlement, the June 26, 2007 Supplement left unchanged White Buffalo's request for $870,667 in profits. 42. On August 30, 2007, the CO made a decision on White Buffalo's Revised

Settlement Proposal, denying White Buffalo's Proposal in part and allowing it in part. The CO denied White Buffalo's lost-profits claim in its entirety.

7
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 9 of 14

43.

White Buffalo is a "party" within the meaning of 28 U.S.C. § 2412(2)(B) and is

entitled to its attorneys' fees herein pursuant to the Equal Access to Justice Act (the "EAJA"). FIRST CLAIM FOR RELIEF (Past Costs--Termination for Convenience) 44. 45. White Buffalo incorporates paragraphs 38 through 43, above. Under F.A.R. 49.201(a), White Buffalo is entitled to be compensated fairly for the

work done on the preparations made for the terminated portion of the Contract, including a reasonable allowance for profit. 46. As set forth in its certified claims, as revised through June 2007, fair

compensation to White Buffalo for the terminated portions of the Contract, including a reasonable allowance for profit on work actually performed, is shown below. No. Item 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Job Costs Direct Labor Indirect Factory Expense Special Tooling and Special Test Equipment Other Costs Surety, Equipment General and Administrative Expenses TOTAL COST (items 1 thru 6) Profit TOTAL (items 7 and 8) Deduct Finished Product Invoiced or to be Invoiced TOTAL (item 9 less item 10) Settlement Expenses TOTAL (items 11 and 12) Settlements with Subcontractors Gross Proposed Settlement (items 13 thru 14) Disposal and Other Credits 8
Portlnd3-1630953.1 0079700-00014

Total Proposed $128,598.08 $128,478.00 $0.00 $0.00 $395,721.00 $28,183.00 $680,980.08 $345,916 $1,026,896.08 $0.00 $1,026,896.08 $163,070.28 $1,189966.36 $39,222.35 $1,229,188.71 $0.00

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 10 of 14

No. Item 17. 18. 19. 47. Net Proposed Settlement (item 15 less 16) Advance, Progress & Partial Payments (from Schedule H) Net Payment Requested (items 17 and 18)

Total Proposed $1,229,188.71 $479,085.00 $750,103.71

On October 30, 2007, the CO allowed and rejected White Buffalo's Proposal as

follows. The line items are not parallel, but in substance, the CO addressed the entirety of White Buffalo's Proposal. Direct Labor: Other Direct Job Costs: Equipment, Vehicle and Fuel: Other Equipment and Vehicle Costs: Surety: G&A Expenses: Subcontractor Claim: Profit: Settlement Expenses: Subtotal: Payments Received: Allowed Amount: 48. $127,463.00 $101,014.00 $26,985.00 $65,808.00 $261,646.00 $28,183.00 $29,528.00 $ 0.00 $78,636.61 $719,263.61 ($479,085.00) $240,178.61

The difference between White Buffalo's Proposal and the amount allowed by the

CO is $509,925.10. Based on the decision of the CO, White Buffalo has revised the amounts claimed for attorneys' fees by an estimated 20 percent, or $18,702.85, and payroll by an estimated 20 percent, or $8,664.38. White Buffalo is entitled to the recovery of the amount of $482,557.87 plus the undisputed amount of $240,178.61, for a total of $722,736.48 plus pre- and post-judgment interest as provided by the CDA and interest and penalties under the Prompt Payment Act. SECOND CLAIM FOR RELIEF (Breach of Contract--Lost Profits) 49. White Buffalo incorporates paragraphs 38 through 43, above.

9
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 11 of 14

50.

FHA breached its implied obligations of good faith and fair dealing and duty to

cooperate in facilitating White Buffalo's performance of the contract, by: a. Refusing to make for White Buffalo the changes in plans and

specifications subsequently made for TWC, as evidenced by the November 2002 Landmark Survey; b. Refusing to acknowledge to White Buffalo the differing site conditions

recognized through accommodating TWC, as later evidenced by the November 2002 Landmark Survey; c. Paying TWC and charging White Buffalo for volumes never excavated, as

later evidenced by the November 2002 Landmark Survey; d. Terminating White Buffalo for default where there were defective plans

and specifications and differing site conditions, as later evidenced by the November 2002 Landmark Survey; and e. Falsely stating to White Buffalo that no design changes had been made

and denying that there were no design-change documents, as later evidenced by the January 2000 FOIA disclosure and the November 2002 Landmark Survey. 51. These breaches prevented White Buffalo from completing the work it contracted

to perform and denied to White Buffalo the profits it would have earned upon full performance of the Contract. 52. A subsequent declaration by FHA converting a termination from a default to one

of convenience termination does not impair a claim to profits lost on work arising from prior government breaches.

10
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 12 of 14

53.

Had White Buffalo been allowed to perform the Contract, it would have earned

profits in the amount of $524,751. White Buffalo is entitled to damages in that amount plus interest under the CDA, interest and penalties under the Prompt Payment Act and its attorneys' fees under the EAJA. THIRD CLAIM FOR RELIEF (Abuse of Discretion--Bad Faith, Loss of Liability Limitation) 54. 55. White Buffalo incorporates by reference paragraphs 39 through 43, above. Under F.A.R. 49.202(a), lost future profits on termination work are not

recoverable as part of a good-faith termination for convenience. 56. Where a convenience termination is the product of bad faith, there is no limit on

recovery of lost future profits. 57. FHA's January 2004 conversion of the termination from default to convenience

was the culmination of a pattern of bad-faith government conduct. Consequently, FHA is not entitled to escape liability for profits shown to have been lost on wrongly terminated future work. 58. Had White Buffalo been allowed to perform, it would have earned profits in the

amount of $524,751. White Buffalo is entitled to damages in that amount plus interest under the CDA, interest and penalties under the Prompt Payment Act and its attorneys' fees pursuant to the EAJA. PRAYER WHEREFORE, White Buffalo requests the following relief. A. On its First Claim for Relief: i. Damages in the amount of $722,736.48;

11
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 13 of 14

ii.

Interest on that sum, or other amount awarded, dating from January 13,

2005, along with interest and penalties under the Prompt Payment Act; iii. iv. B. White Buffalo's attorneys' fees under the EAJA and costs herein; and Such further relief as the Court deems appropriate.

On its Second Claim for Relief: i. A finding that FHA has breached its implied contractual obligations of

good faith and fair dealing; ii. A declaration that FHA's conversion of a termination from default to

convenience cannot and does not extinguish government liability for profits lost from breaches of contract occurring prior to the declaration of default; iii. iv. Recovery of $524,751 in profits lost on wrongfully terminated work; Interest on that amount, or other sum awarded, dating from January 13,

2005 plus interest and penalties under the Prompt Payment Act; v. vi. C. Its attorneys' fees under the EAJA and costs herein; and Such further relief as the Court deems appropriate.

On its Third Claim for Relief: i. ii. A finding that FHA has acted in bad faith; A declaration that FHA therefore cannot invoke the exclusion of lost

future profits from amounts to be awarded under a convenience termination; iii. iv. Recovery of $524,751 in profits lost on wrongfully terminated work; Interest on that amount, or other sum awarded, dating from January 13,

2005 plus interest and penalties under the Prompt Payment Act; v. Its attorneys' fees under the EAJA and costs herein; and

12
Portlnd3-1630953.1 0079700-00014

Case 1:07-cv-00738-LAS

Document 15-2

Filed 07/10/2008

Page 14 of 14

Vi.

Such further relief as the Court finds appropriate. ,2008. STOEL RIVES LLP

DATED:

Richard E. Alexander, OSB No. 69002 Scott 1. Kaplan, OSB No. 913350 Attorneys of Record for White Buffalo Construction, Inc. Richard E. Alexander, Attorney of Record Scott 1. Kaplan, Attorney of Record Stoel Rives LLP 900 SW Fifth Avenue, Suite 2600 Portland, OR 97204-1268 Telephone: (503) 224-3380 Facsimile: (503) 294-9167

13
Portlnd3-1630953.l 0079700-00014