Free Order - District Court of Connecticut - Connecticut


File Size: 226.2 kB
Pages: 52
Date: November 17, 2006
File Format: PDF
State: Connecticut
Category: District Court of Connecticut
Author: unknown
Word Count: 10,297 Words, 65,600 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/ctd/9481/120-1.pdf

Download Order - District Court of Connecticut ( 226.2 kB)


Preview Order - District Court of Connecticut
Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 1 of 52

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT STEWARD MACHINE CO., INC., Plaintiff, v. WHITE OAK CORP. and NATIONAL UNION FIRE INSURANCE CO. OF PITTSBURGH, PA, Defendants. MEMORANDUM OF DECISION Steward Machine Co., Inc. ("Steward") has sued White Oak Corp. ("White Oak") and White Oak's surety, National Union Fire Insurance Co. of Pittsburgh, PA ("National Union"). The action arises out of the construction of the Tomlinson Bridge in New Haven, Connecticut. In 1994, the Connecticut Department of Transportation ("ConnDOT" or "the State") engaged White Oak to be the project's general contractor. White Oak then procured a payment bond, with National Union as surety, and sub-contracted with Steward for the latter to furnish certain machinery for the project. Steward filed suit against the defendants seeking damages for White Oak's failure to pay Steward in full on a timely basis, White Oak's failure to accept delivery of the machinery, and the lengthy, ensuing storage of the Tomlinson Bridge machinery at Steward's plants. The parties tried the case to the court over six days. My findings of fact and conclusions of law are set forth below. See Fed. R. Civ. P. 52. I. Background The parties presented conflicting testimony regarding the effect of their contracts. My findings of fact are largely based on the written purchase order contract, documents relating to CIVIL ACTION NO. 3:00cv834 (SRU)

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 2 of 52

the contracts at issue, the parties' written correspondence, and the testimony of Steward's President Whitney DeBardeleben, whom I find credible. A. Parties' Involvement with the Tomlinson Bridge Project

Steward is a family-owned, specialized job shop located in Birmingham, Alabama. Among other large-scale items, Steward manufactures mechanical equipment, including sheaves and counterweight ropes, for moveable bridges. During the design phase of the Tomlinson Bridge project, the engineering firm Hardesty & Hanover, the project's design engineers, contacted Steward to inquire about the feasibility of the bridge design plans. As a result of that contact, Steward became interested in the project. Once the engineers submitted their design to the State, ConnDOT solicited bids from general contractors. Steward submitted its bids to the general contractors that were bidding on the project, including White Oak. ConnDOT eventually awarded White Oak the contract for State Project 92-435, the construction of the Tomlinson Bridge in New Haven, Connecticut. As required by Conn. Gen. Stat. § 49-41, White Oak secured a payment bond to guarantee the public work project. On June 6, 1994, National Union issued that payment bond, guaranteeing the project in the amount of $87,868,378.10. Pl. Ex. 1. B. Purchase Order Contract

White Oak subcontracted with Steward for the latter to furnish large-scale equipment for the Tomlinson Bridge. On August 8, 1994, Steward and White Oak executed a written purchase order contract setting forth the details of the parties' subcontract. Pl. Ex. 3.

-2-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 3 of 52

1.

ConnDOT Approval

The introductory paragraph of the purchase order specifies that the bid items "shall be in accordance with the plans and specifications prepared by" ConnDOT, the project owner. Pl. Ex. 3 at 1. 2. Bid Items and Prices

The purchase order contract included four items and a delivery allowance. Id. The four items were identified by ConnDOT bid item numbers, corresponding to the items as listed on White Oak's prime contract with the State. With their corresponding values, the items were: Operating machinery Main and auxiliary counterweight ropes and accessories Counterweight sheaves, shafts and bearings Lock machinery Total for bid items 3. Delivery $1,215,000 1,465,000

4,400,000 253,000 $7,333,000

In addition to the four bid items, the purchase order included a delivery allowance in the amount of $220,000. Thus, the value of the purchase order contract totaled $7,553,000. The purchase order contract included the following provision regarding delivery: Delivery will commence within 12 months from approval of drawings and be complete within 18 months from approval of drawings. Seller shall make all deliveries in accordance with the Buyer's schedule. Pl. Ex. 3 at 6.

-3-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 4 of 52

White Oak and National Union have argued, in essence, that the second sentence of the delivery provision ("Seller shall make all deliveries in accordance with the Buyer's schedule.") overrides the first sentence. Accordingly, the defendants argue that Steward (the Seller) agreed to abide by White Oak's (the Buyer's) delivery schedule even if that schedule included a delay of several years after the approval of drawings. In other words, they argue that Steward ­ not White Oak ­ bore any risk of delay. Based on the language of the purchase order's delivery provision and the testimony of DeBardeleben, however, I find that the parties did not agree to an indefinite delivery date or one that could extend several years beyond the twelve- to eighteen-month window set forth in the contract's delivery provision. The parties' contract provided that Steward would make deliveries in accordance with White Oak's schedule, with respect to each bid item, but that schedule was limited to the six-month period commencing twelve months after the approval of Steward's drawings. The approval of drawings for each bid item spanned several years. The last approval of drawings for the lock machinery was May 15, 1998; the last approval of drawings for the sheaves was January 29, 1996; the last approval of drawings for the counterweight ropes and accessories was March 19, 1996; and the last approval of drawings for the operating machinery was January 6, 2000. Def. Ex. 785. White Oak had until eighteen months after each of those dates to request and accept delivery of the respective bid item. Thus, under the purchase order contract, delivery of the lock machinery was to occur by November 16, 1999; delivery of the sheaves was to occur by July 30, 1997; delivery of the counterweight ropes was to occur by September 20, 1997; and delivery of -4-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 5 of 52

the operating machinery was to occur by July 7, 2001. 4. Terms and Conditions a. Terms of Payment and Effect of Payment from ConnDOT

The purchase order contract included the following terms of payment: Buyer [White Oak] will cooperate with Seller [Steward] to submit requests for payment on a timely basis to Owner [ConnDOT] for all items of work incorporated herein or a portion thereof. Invoices will be paid within 10 days of receipt of payment by Buyer from Owner for said items of work or 60 days from invoice date, which ever [sic] is sooner. Any portion of the purchase price Buyer may be entitled to retain shall become due and payable upon acceptance of all goods purchased under this agreement or within 180 days after final shipment, whichever event occurs first in time. Pl. Ex. 3 at 7, ¶ 3. At trial, there was conflicting testimony regarding White Oak's responsibility for payment under the contract. Defense witnesses testified that White Oak was merely a conduit that forwarded invoices from Steward to ConnDOT and paid Steward only what it received from ConnDOT as payment for Steward's work. They testified that White Oak was not responsible for any amounts beyond what ConnDOT paid. Paul Mayotte, former Chief Financial Officer of White Oak, testified that the sixty-day term, described in the purchase order, was "academic," and that he understood that if ConnDOT did not pay for Steward's work, White Oak was not required to pay Steward. Robert Hackling, a White Oak project manager, testified that White Oak would pass payment to Steward from ConnDOT, but that the State would not pay Steward for work unless the equipment was fully fabricated. He testified that White Oak complied with the purchase order because it made payment in full for all the money received from ConnDOT for Steward

-5-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 6 of 52

equipment. The defendants also offered many letters from White Oak to ConnDOT, requesting payments for Steward's work, as well as responses from ConnDOT, in order to show White Oak's compliance with the contract. DeBardeleben testified, however, that White Oak was responsible for payment within ten days from receipt of payment by ConnDOT or sixty days from the invoice date, whichever occurred first. DeBardeleben disputed the claim that White Oak was not responsible for invoiced amounts not covered by the State. He testified that payment by ConnDOT was not a prerequisite to White Oak's obligation even though Steward understood that White Oak would invoice ConnDOT for Steward's work and Steward cooperated with White Oak's billing. I credit the testimony of DeBardeleben, which is consistent with the language of the contractual provision regarding terms of payment. I find that White Oak agreed to pay properly invoiced amounts within sixty days after the invoicing or within ten days of receiving payment by ConnDOT, whichever occurred first. Action or inaction on the part of ConnDOT did not affect the later, sixty-day deadline. Finally, I find that White Oak did, in fact, invoice ConnDOT for Steward's work, but that some of the funds received from the State for the subcontractor's work were not passed on to Steward within ten days. b. "Work in Progress" Payments and Percentages Complete

During contract negotiations, Steward provided White Oak with a quotation that included provisions concerning "progress payments." Pl. Ex. 56. The final purchase order did not include a specific provision regarding progress payments. It did, however, include the following terms, -6-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 7 of 52

which imply that the parties agreed to interim payments: Terms of payment ­ Buyer will cooperate with Seller to submit requests for payment on a timely basis to Owner for all items of work incorporated herein or a portion thereof. Invoices will be paid . . . . Pl. Ex. 3 at 7 ¶ 3 (emphasis added). Performance Of Work ­ No payment, final or otherwise, made under or in connection with this contract shall be conclusive evidence of the satisfactory performance under this contract either in whole or in part . . . . Id. at 8 ¶ 10 (emphasis added). Steward invoiced White Oak before completion and delivery of the items, and White Oak made partial, or progress, payments. Certificates of title included with each invoice transferred title of the specified percentage complete to White Oak. E.g., Pl. Ex. 51 at 3, ¶¶ 1-2. The invoices and payments were based on the individual bid item's "percentage complete," that is, the estimated degree of completion of the fabrication, stated in percentage terms. A ConnDOT representative was present at Steward's plants throughout the fabrication and machining of the Tomlinson Bridge equipment. That inspector confirmed and recorded the bid items' percentages complete. The percentages complete on the final invoices of three of the bid items were: operating machinery, 68% complete, Def. Ex. 457; sheaves, 100% complete, Def. Ex. 420; and lock machinery, 85% complete, Pl. Ex. 51.1 When Steward and White Oak's disputes regarding delay and non-payment had reached an impasse, ConnDOT contracted with Cianbro Corp. to complete the fabrication of the machinery held at Steward's plants. After May 2000, Robert Pellerin, then a project superintendent at Cianbro, visited Steward's plants on behalf of ConnDOT. The purpose of
1

The final invoice for the counterweight ropes did not specify a percentage complete. -7-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 8 of 52

Pellerin's visit was to determine the amount of work necessary for Cianbro to complete the fabrication of the equipment. Pellerin took photos of the equipment. Def. Ex. 673. He also noted his determinations of the percentages complete for purposes of calculating the remaining work that Cianbro would perform. Def. Ex. 620 (Pellerin's notations in dark pen). Pellerin revised the percentages complete as follows: sheaves primary speed reducers secondary speed reducers main pinions ring gears pinion bearings couplings 70% 90% 90% 95% 85% 100% 100%

Pellerin did not note any percentages complete with respect to the other items or components. Pellerin testified at trial regarding the completion percentages. When asked if there was any reason for Cianbro to disagree with the percentages complete previously determined by the State, Pellerin testified that his notations represented what he thought it would take Cianbro to complete the project. He also stated that manufacturers receive higher completion percentages because of the high cost of raw materials. In other words, Pellerin did not testify that the percentages complete that had been calculated by the ConnDOT representative ­ and which were the basis of Steward's invoices ­ were inaccurate. Rather, he testified that manufacturers, such as Steward, are awarded higher completion percentages, thereby permitting the earlier release of payment to them, because of the high cost of raw materials that they must purchase up front for the project. Furthermore, the -8-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 9 of 52

purpose of Pellerin's calculations was not to determine the cost to Steward or the amount of fabrication that Steward had completed; rather, his numbers reflected an estimation of the cost for Cianbro to complete the project. Cianbro's incentive to over-estimate the work remaining on the equipment in order to maximize its revenue suggests that Pellerin's later determinations are less accurate. National Union also relies on a ConnDOT audit, dated February 5, 1999, in which a state representative evaluated the completion percentages of the bid items, to argue that Steward inflated the completion percentages when billing White Oak. Def. Ex. 620 (typed percentages). That audit was conducted after the parties' dispute was full blown. I credit the percentages complete originally determined by the state inspector. Steward's invoices were not based on inflated completion percentages, and the percentages invoiced were authorized by the project owner's representative on site at Steward's plants. c. Retainage

Although the details were absent from the purchase order, the terms of payment referred to "[a]ny portion of the purchase price [White Oak] may be entitled to retain," and all parties agreed that White Oak was entitled to retain 2.5% of invoiced amounts. Pl. Ex. 3 at 7, ¶ 3. That retainage became payable to Steward "upon acceptance of all goods purchased under this agreement or within 180 days after final shipment whichever event occurs first in time." Id. d. Service Charge

The purchase order included the following provision in case of delinquent payment: In the event Buyer fails to make payment in accordance with the terms of this agreement, the account shall be deemed to be delinquent and a service charge of one percent (1%) per month will be added to the unpaid balance. Where a -9-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 10 of 52

service charge of one percent per month exceeds the maximum allowed by law, the service charge shall be the maximum allowed. Id. at 7, ¶ 6. Witnesses provided varying testimony regarding the meaning of "one percent (1%) per month." Mayotte, White Oak's former CFO, testified that he understood the one-percent charge to be a "one-time charge," not running interest. Witnesses from Steward testified that the purchase order provided for one-percent interest on unpaid balances. Steward's invoices reflected interest compounded monthly. In addition, in a letter dated September 16, 1997, Mayotte wrote to Steward's Jerry Shivers: To the extent that White Oak has failed to pay these amounts in accordance with Par. 3 of the [purchase order] agreement, we have an obligation for service charges for the unpaid amount(s) at 1% per month as per Par. 6. Def. Ex. 494A (emphasis added). The schedule attached to that letter included a column that itemized the amount of "interest" due. Id. Based on the language of the purchase order, the testimony of Steward witnesses, and the language of Mayotte's letter, I find that, in case of partial payment or non-payment, the purchase order contract provided for one-percent interest (dubbed "a service charge"), compounded monthly and added to the unpaid balance. C. Prime Contract

White Oak's contract with ConnDOT ­ the prime contract ­ included, among other items, the four bid items listed in the Steward purchase order contract. The prices set forth in the prime contract, however, did not correspond to the prices in the purchase order. In the prime contract, the items were priced:

-10-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 11 of 52

Operating machinery Counterweight ropes Sheaves Lock machinery Def. Ex. 494 (attached schedule).

$1,700,000 $600,000 $5,000,000 $400,000

The sheaves, operating machinery, and lock machinery were priced higher in the prime contract; the counterweight ropes were priced higher in the purchase order contract. The differences between the two contracts' schedules of values were as follows: Operating machinery Counterweight ropes Sheaves Lock machinery D. Invoices and Percentages Complete $485,000 ($865,000) $600,000 $147,000

Steward's first invoice, dated November 30, 1994, listed the sheaves as 18% complete. Pl. Ex. 52. Accordingly, Steward billed White Oak $792,000, i.e., 18% of the sheaves' $4.4 million purchase order value. Id. The invoices from January 18, 1995 through June 17, 1996 did not specify the completion percentages. Invoices issued from August 18, 1996, through June 8, 1998, did specify the items' percentages complete based on the inspectors' reports. Those invoices followed a "reallocation" of bid item values, discussed below. The final invoices for the lock machinery, sheaves, and operating machinery used the reallocation and reflected the following percentages complete: operating machinery, 68%

-11-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 12 of 52

complete, Def. Ex. 457; sheaves, 100% complete, Def. Ex. 420; and lock machinery, 85% complete, Pl. Ex. 51.2 Plaintiff's Exhibit 53, attached to this decision as Appendix A, summarized Steward's invoices, amounts due, payments, and accumulated interest. That summary did not list the completion percentages.3 E. Certificates of Title

DeBardeleben testified that each invoice included a certificate of title, and that those certificates transferred title of the specified percentage complete to the State. The certificate of title enclosed with the lock machinery invoice dated June 8, 1998, however, transfers to transfer title to White Oak: The Vendor has executed this document for the purpose of acknowledging that the Vendor has made an outright sale and transfer of title of the above described materials lawfully owned by the Vendor to the Contractor . . . . Pl. Ex. 51 at 3, ¶ 1. The Contractor certifies and represents that he is the lawful holder of the absolute legal title to the above described materials and has the full legal right, power and authority to sell and transfer title to the same . . . . Id. at ¶ 2. Defense exhibits also show that the certificates of title transferred title from Steward to White Oak. E.g., Def. Exs. 281, 292 & 320.

The last invoice for the counterweight ropes was issued June 17, 1996, prior to the reallocation, and did not specify a percentage complete. In connection with a post-trial submission, requested by the court, Steward submitted a revised Exhibit 53. In that revised submission, Steward made corrections to the exhibit. All citations to Exhibit 53 refer to the revised exhibit. -123

2

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 13 of 52

F.

April 1997 Meeting

Prior to April 11, 1997, Steward learned that ConnDOT had paid to White Oak $675,470.91 "for materials furnished by Steward." Pl. Ex. 34. White Oak had not, in turn, paid Steward the sum due Steward under the purchase order due to a "cash flow problem." Later that month, Whitney DeBardeleben, Charles DeBardeleben, and Shivers met in New Haven with representatives of White Oak, including White Oak's former President, Jack Morrissey, to discuss White Oak's payments to Steward. At that meeting, Morrissey agreed that White Oak would pay $25,000 per week toward past due interest in order to bring the account up to date. G. Reallocation

As discussed above, Steward understood that White Oak would receive payment from ConnDOT for work performed by Steward. The language of the contract reflects the parties' anticipation that White Oak would receive payment for Steward machinery from ConnDOT and forward that payment to Steward: "Buyer will cooperate with Seller to submit requests for payment on a timely basis to Owner for all items of work incorporated herein or a portion thereof." Pl. Ex. 3 at 7, ¶ 3. During the project, difficulties arose with respect to payment from ConnDOT. White Oak forwarded Steward's invoices to ConnDOT for payment, but ConnDOT issued payments based on the prices listed in the prime contract, not the prices from White Oak and Steward's purchase order. White Oak did not have sufficient funds to pay Steward's invoices in full. In response, the parties sought to match amounts payable to Steward with amounts receivable from ConnDOT -13-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 14 of 52

in an effort to permit White Oak to collect more money from the State and to facilitate White Oak's payments to Steward. Without amending the purchase order, the parties adjusted the itemized prices in the purchase order to match the prices listed in White Oak and ConnDOT's prime contract. For example, a post-reallocation invoice billed for work on the sheaves based on a total price of $5,000,000 ­ the prime contract's price for the sheaves ­ even though the purchase order priced the sheaves at only $4,400,000. Def. Ex. 420. The so-called reallocation was memorialized in a letter from Steward to White Oak, dated January 8, 1998. Pl. Ex. 41. The reallocation did not affect the purchase order contract's total price, which remained $7,333,000 (excluding the $220,000 the delivery allowance). A discrepancy arose, however, because the total of the adjusted purchase order prices for the bid items was $7,700,000. Pl. Ex. 41. The plaintiff referred to this discrepancy as an "overage." In other words, the parties' reallocation failed to account for the overall difference between the total value of the items in the purchase order and the total value in the prime contract, a difference of $367,000. Steward issued a credit (denoted "CM") in an effort to compensate for the difference between the prime contract and purchase order values. Pl. Ex. 52; Def. Ex. 780. The credit was in the amount of $338,529.74 and was associated with job number 5344, the counterweight ropes. There were no further invoices submitted with respect to the counterweight ropes following the credit. H. Alleged Overbilling

There was some testimony regarding alleged overbilling by Steward. Mayotte testified that Steward was only entitled to receive payment in the amount that ConnDOT would pay to White Oak, and he classified invoices in amounts greater than what ConnDOT paid as -14-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 15 of 52

overbilling. The witness acknowledged, however, that Steward's billing was not fraudulent; it was merely higher than what ConnDOT paid to White Oak. The defendants also introduced as evidence a letter dated December 11, 1997, in which Morrissey disputed the amount claimed by Steward and accused Steward of overbilling in the amount of $580,243.30, charging interest on the overbilling, and applying "material" payments to interest. Def. Ex. 509. The so-called overbilling was a result of the parties' effort to collect more money from the State to pay Steward's invoices. Steward did not bill for work that was not completed, although it did charge amounts that were greater than the purchase order values associated with the bid items. As a result, Steward also charged interest on unpaid balances that were based on invoice amounts in excess of the prices in the parties' purchase order contract. I. Manufacture and Delay

Steward began manufacturing the Tomlinson Bridge equipment in 1994. By September 1996, the sheaves ­ the first items required at the job site and those that required the most work by Steward ­ were principally ready for shipment to the job site. White Oak, however, was not prepared to receive the sheaves. Therefore, Shivers, the White Oak project manager charged with overseeing the project, and Morrissey, White Oak's President, discussed with DeBardeleben the possibility of storing the machinery at Steward. When it became "inevitable" that Steward would store the machinery, Morrissey told DeBardeleben that Steward would be paid for storage costs.

-15-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 16 of 52

J.

Storage 1. Ancillary Storage Agreement

In October and November of 1996, Shivers wrote several letters to White Oak's George Hird addressing the options for storage and the associated costs. In a letter dated September 12, 1996, Shivers wrote Hird to request any "special storage requirements" from the State and indicated that the stored machinery, including the eight counterweight sheaves, would be moved from inside to outside Steward's shop. Pl. Ex. 14. In a letter dated October 30, 1996, Hird wrote Shivers, requesting Steward's "recommendations for long term storage (one year approx.)." Def. Ex. 415. In a letter dated October 31, 1996, and in response to a letter from ConnDOT, Shivers listed three options for maintaining the counterweight sheaves while they were stored outside: (1) to do nothing and sandblast surfaces prior to painting; (2) to coat the unmachined surfaces with petroleum-based oil and to monitor them throughout the duration of the storage; or (3) to sandblast and primer coat the sheaves, requiring re-painting of the sheaves after installation. Pl. Ex. 16. ConnDOT's Paul H. Breen wrote to White Oak, indicated that the State preferred the second option, and noted that costs for the temporary storage and protection were "assumed by the Contractor until such time that it can be clearly shown that the associated delays resulted from the action or inaction" of ConnDOT. Pl. Ex. 18. In a memorandum dated November 18, 1996, Hird wrote to Shivers to instruct him to pursue the storage with petroleum-based coating protection (i.e., "option no. 2") and "acknowledge[d] that the sheaves must be stored at [Steward] beyond the original delivery date and that there are certain additional costs associated with the storage which could not have been anticipated by Steward Machine." Pl. Ex. 20. -16-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 17 of 52

In a letter dated November 15, 1996, Shivers described the machinery being stored, the square footage required for storage (6,577 square feet), and quoted a rate of $8/square foot for indoor storage. Pl. Ex. 19. In a letter dated December 12, 1996, a Steward representative4 listed parts associated with the counterweight ropes and accessories and the square footage required for their storage (302 square feet), as well as rates of $8/square foot for indoor storage and $5/square foot for outdoor storage. Pl. Ex. 21. The second page to that exhibit (titled "Tomlinson Bridge Storage Charges Recap"), which appears to have been included as an attachment to the letter, listed the square footage required for the lock machinery (192 square feet). Id. White Oak never negotiated or protested the quoted prices despite receiving Steward's storage invoices from September 1996 through mid-2000. White Oak forwarded the storage invoices to ConnDOT for payment. Steward charged White Oak interest on unpaid storage charges at one-percent, compounded monthly, based on the interest rate of the purchase order contract. White Oak never paid any of Steward's storage invoices or otherwise compensated Steward for any storage costs. 2. Storage at Steward

Steward based the storage charges on over 7,900 square feet, the "footprint" of the Tomlinson Bridge machinery, which equaled approximately four to five percent of the floor space at Steward's facilities. The sheaves were by far the largest items that Steward stored for White Oak. At different points during the storage period, the sheaves were moved outside, stored in the parking lot, and

The plaintiff introduced only a portion of the letter, and that portion did not include the author's name. -17-

4

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 18 of 52

then returned inside Steward's plants. The sheaves were held inside Plant One in September and October 1996, then moved two miles across town and stored outside Plant Two beginning in December 1996. While outside, the sheaves were jacked off the ground, anti-rust was applied, and wooden frames with tarps were constructed to protect the sheaves from moisture and debris. The sheaves were moved back inside prior to being shipped to Connecticut. The trunions ­ a component of the fully assembled sheaves ­ were over eight feet in length and 34.4 inches in diameter and weighed approximately twelve tons each. Because storage and transportation would be difficult once the trunions were placed into the sheaves, Steward chose not to complete their final assembly until just prior to shipment. Prior to the final assembly, the trunions were stored in Plant One. The reducers ­ a component of the operating machinery ­ were also ready to be assembled and shipped, but were stored inside. The gear boxes ­ some assembled, some unassembled ­ were scattered throughout the shop, awaiting final assembly and shipment. Eventually, Steward refused to ship the Tomlinson Bridge machinery despite the fact that the presence of the Tomlinson Bridge equipment, as discussed below, interfered with Steward's other manufacturing projects. In July 1999, Steward refused to release certain pieces of the machinery in response to requests for delivery. Shivers wrote that the items would not be shipped until the storage costs and interest were paid. Def. Ex. 612. In the summer of 2000, a representative of National Union visited Steward, seeking the release of the machinery. In May 2000, White Oak and National Union filed suit against Steward, seeking immediate possession of the Tomlinson Bridge machinery ("the Replevin Action"). In August 2000, the parties settled the Replevin Action and the machinery was shipped to Connecticut. Def. Ex. 565. -18-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 19 of 52

Steward regularly invoiced White Oak for the cost of storage from September 1996 through August 2000. Steward did not invoice the maintenance and storage costs separately; in other words, any maintenance charges were subsumed within the $8 and $5 per square foot storage charges. Although there was testimony that the $8 and $5 rates were used for indoor and outdoor storage respectively, all of the invoices appear to have used the $5 rate or a blended rate. Pl. Ex. 54 (summary of storage invoices). 3. Impact of Storage on Steward

Steward's plants did not have space available for long-term storage of massive machinery, and the storage of the Tomlinson Bridge machinery caused inconvenience and disruption at Steward's plants, affecting its performance on other jobs. Discussion of the equipment and its problems occurred on a near-weekly basis at production meetings from October 1996 through 2000. Steward was forced to maneuver other projects around the Tomlinson Bridge equipment and "do upkeep" on the Tomlinson Bridge equipment, including applying anti-rust. The obstruction caused by the racks impeded the movement of other jobs throughout the shop, and Steward needed to keep track of the Tomlinson Bridge pieces over several years. In a letter dated June 14, 1999, Shivers described the storage of the Tomlinson Bridge machinery and the difficulty of measuring the impact of that storage on Steward's production. Shivers enclosed a list of jobs completed in 1996, 1997, and 1998, on which he highlighted "the larger jobs that were impacted" by the Tomlinson Bridge equipment. Def. Ex. 663. The cost of each of those jobs was greater than the selling price, and Shivers posited that the inconvenience resulting from the presence of Tomlinson Bridge machinery caused some portion of the excess -19-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 20 of 52

cost. The defendants presented evidence that tended to minimize the effect of the Tomlinson Bridge equipment on Steward's other jobs. Steward was not prevented from bidding on other projects due to the interference of the Tomlinson Bridge machinery. Several letters from Steward to other customers detailed manufacturing problems and delays that were not attributable to the presence of the Tomlinson Bridge machinery. E.g., Def. Exs. 3, 9, 12. One letter referred to the "stand still" of the "entire shop" due to the interference of machinery from another customer's project, Def. Ex. 31, but the whole shop was not, in fact, at a stand still. In an effort to quantify the cost of the Tomlinson Bridge machinery on its bottom line, Steward created a new work order number to which employees were instructed to charge their time while working on maintaining the Tomlinson Bridge equipment, moving the equipment bring stored, or otherwise navigating around it. Claimed costs associated with storage included $119,580.27 in labor; $13,579.49 in materials; and $6,405.35 for a subcontract for crane rental. Pl. Ex. 55 (job detail history report).5 After Steward calculated overhead with a burden rate of over $5, the total claimed costs increased to over $750,000.6 Id. Defense expert Frank Zito, a Certified Public Accountant, testified regarding the maintenance costs charged to the work order number assigned to the storage of the Tomlinson Bridge machinery. Zito testified that most of the work tracked on the job history report appeared

The materials cost of $14,634.90 erroneously includes an expense payment to Shivers in the amount of $1,055.41. The correct materials costs is, therefore, $13,579.49. There was testimony concerning the burden rate used in the job history report and the significantly lower burden rate used by the parties' accounting experts. As set forth in the discussion below, it is unnecessary for me to evaluate Steward's burden rate. -206

5

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 21 of 52

to be work due under the base contract, not maintenance or storage-related work. Zito testified that some of the timecards associated with the work order number had "storage" or "refurbishment" notations, while others did not. In response, DeBardeleben testified that some descriptions, such as "welding," were automatically generated when certain classes of workers punched their timecards.7 K. Work Performed While Machinery Was in Storage

After April 1997, when it was apparent that the machinery would not soon be shipped to Connecticut, Steward essentially stopped work on it. There was, however, some work completed on the lock machinery in March or April 1998. In addition, machining operations were completed on the racks ­ components of the operating machinery ­ through 2000, though not continuously. Machining on the racks was never finished because, absent a shipping date, other jobs took priority over the Tomlinson Bridge project. Additionally, once the ring gears' legs and teeth were cut, the individual pieces became increasingly delicate and difficult to store. The defendants have acknowledged that Steward completed piece-meal work from January 1997 through August 2000 that was not limited to storage or maintenance, but extended
7

Additionally, I note that Steward sought to introduce the testimony of Les Alexander, an accounting expert, on the question of the effect of the Tomlinson Bridge equipment on Steward's productivity. In an effort to quantify the damages suffered as a result of the impact on Steward's ongoing fabrication, Steward retained Alexander, who specializes in forensic accounting. On the defendants' Daubert motion, I excluded Alexander's testimony regarding business disruption and inefficiency on the ground that the methodology he used was not reliable. See Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579 (1993). The plaintiff was not prevented from introducing Alexander's testimony with respect to the maintenance costs incurred, and I permitted Alexander to testify about his methodology at the plaintiff's request. Having heard Alexander's testimony at trial and having considered his report on the business disruption and inefficiency in its entirety, I concluded that the report did not meet the necessary standard of reliability under Daubert. Additionally, as finder of fact, I found the report unpersuasive even if it were admitted into evidence. -21-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 22 of 52

to base contract work required by the purchase order. National Union Trial Brief at 25. L. Notice of Claim

On April 16, 1997, Charles DeBardeleben wrote Morrissey, seeking payment of approximately $675,000.00 that White Oak had received from ConnDOT for Steward's work but that White Oak failed to pass on to Steward. Pl. Ex. 34. Charles DeBardelben specifically noted that the letter was "notice of Steward's claim for payment" pursuant to section 49-41a of the Connecticut General Statutes, and demanded that White Oak place the funds in an interestbearing escrow account if payment were not made within ten days. Steward continued to complete work on the Tomlinson Bridge machinery on a limited basis after April 1997. Steward also stored the equipment at its plants ­ at White Oak's request ­ after April 1997. On December 20, 1999, Steward filed a notice of claim with National Union because of White Oak's default under the purchase order contract and failure to pay Steward's storage costs. Pl. Ex. 2. At trial, Whitney DeBardeleben testified that it was that letter, rather than the April 1997 one, through which Steward terminated the purchase order contract. Prior to the December 20, 1999 notice of claim, White Oak had not paid Steward for its work under the purchase order contract since June 1998. White Oak had never paid any of Steward's invoices for storage costs. In May 2000, Steward commenced the present action, filing suit against National Union on the payment bond and against White Oak on the purchase order ("the Bond Action"). M. Settlement in Replevin Action

In July 2000, White Oak and National Union commenced the Replevin Action, seeking immediate possession of the machinery stored at Steward's plants. White Oak and National Union moved for an expedited prejudgment remedy of replevin. On August 7, 2000, Magistrate Judge William I. Garfinkel issued an order granting the motion for replevin, which Steward -22-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 23 of 52

appealed. The parties eventually reached a settlement agreement in the Replevin Action. Def. Ex. 565. In that settlement agreement, National Union paid Steward $750,000 to be "applied first in reduction of any recovery by Steward against National in the Bond Action." Def. Ex. 565 at 8, ¶ 10. The parties agreed not to seek to recover in the Bond Action any damages accruing after the date of the agreement. Id. at 9, ¶ 12 (dated Aug. 24, 2000).8 They also agreed to approach the court jointly to request a reasonably early trial. Id. at 9, ¶ 14. Under the settlement agreement, Steward was not required to furnish four components of the counterweight ropes and accessories. Def. Ex. 565 at 4-5. The settlement agreement did not associate any particular values to the scope of work that Steward was relieved from performing, and there was no effort to price the previously completed work in connection with the settlement agreement. The settlement agreement did require National Union to pay Steward $1,025,429 in consideration of Steward's performance of refurbishment of the machinery. Def. Ex. 565 at 4-7, ¶¶ 1-5. II. Discussion Steward filed its suit in federal court, and this court has subject matter jurisdiction based on the parties' diverse citizenship. 28 U.S.C. § 1332.

The defendants have argued that the settlement agreement precludes the recovery of contractual and statutory interest accruing after its execution, August 24, 2000. There was no testimony regarding that contractual provision or whether the parties intended it to preclude statutory interest. In their settlement agreement, the parties did, however, agree to approach the court to request a reasonably early trial. I infer from that provision that the parties intended a prompt resolution to their dispute because interest on any outstanding balance had ceased accruing. In other words, I find that the parties intended to cut off interest on any unpaid balances from the execution of the settlement agreement. See Paulus v. LaSala, 56 Conn. App. 139, 147 (1999) ("if interest is due, it is an element of damages"). -23-

8

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 24 of 52

Steward has put forth several theories as bases for its claims that White Oak and National Union owe the plaintiff money damages. First, Steward argues that, because White Oak breached the purchase order contract, White Oak and its surety, National Union, are liable for the unpaid balance of the purchase order, including principal and interest. Second, Steward argues that White Oak and National Union are liable for storage fees. Steward submits that White Oak contracted with it to store and maintain the Tomlinson Bridge machinery when the general contractor was unable to receive the items at the job site. Steward claims the storage costs as damages under either a modification of the original purchase order contract or a collateral storage contract. Steward argues that both White Oak and National are liable for the unpaid storage fees, whether awarded for breach of the modified purchase order or the collateral agreement. Alternatively, Steward argues that White Oak and National Union are liable for the storage fees under the Uniform Commercial Code, Conn. Gen. Stat. §§ 42a-2-708 and 42a-2-710, because the fees are incidental damages that were caused by White Oak's delay and refusal to accept delivery of the Tomlinson Bridge machinery. Third, Steward claims damages under a theory of lost efficiency, alleging that, due to the delays on the project, Steward lost profits on other jobs that were disrupted because of the longterm presence of the Tomlinson Bridge machinery at Steward's plants. Fourth, Steward makes claims for interest based on the purchase order contract or for costs and interest based on Conn. Gen. Stat. § 49-42.9 Steward likewise claims that attorneys'

Steward also makes a claim for offer-of-judgment interest pursuant to Conn. Gen. Stat. § 52-192a. Pursuant to the Local Rules of this District, I am not aware of the amount of the offer -24-

9

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 25 of 52

fees are due either under the purchase order or pursuant to Conn. Gen. Stat. §§ 49-41a and 49-42. A. Unpaid Balance Under Purchase Order Contract 1. White Oak's Breach of the Purchase Order Contract

The elements of a breach of contract action are the formation of an agreement, performance by one party, breach of the agreement by the other party, and damages. E.g., Rosato v. Mascardo, 82 Conn. App. 396, 411 (2004) (internal quotation marks and citation omitted). Steward and White Oak contracted for the construction of the equipment described in the parties' purchase order. Despite the absence in the purchase order of an explicit provision regarding progress payments, the provisions, quoted infra, that refer to "invoices" and requests for payment of a "portion" of the work, coupled with the parties' conduct, confirm that the parties' contract called for interim payments. See Poole v. City of Waterbury, 266 Conn. 68, 97 (2003) ("The intention of the parties manifested by their words and acts is essential to determine the meaning and terms of the contract and that intention may be gathered from all such permissible, pertinent facts and circumstances."). The precise language of the contract also called for payments to be made within sixty days after the invoicing or within ten days of White Oak's receipt of payment by ConnDOT, whichever occurred first. The purchase order did not include a typical "pay-if-paid" or "paywhen-paid" provision, see Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc., 239 Conn.

of judgment. See D. Conn. L.R. Civ. P. 68 (offer of judgment remains under seal until after trial). After entry of judgment, I will examine the offer of judgment to determine whether Steward is entitled to recovery under section 52-192a. See Tureck v. George, 44 Conn. App. 154, 162 (1997) (interpreting "after trial" to mean after a "final judgment").

-25-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 26 of 52

708, 718 (1997), although White Oak was obligated to pay promptly after receipt of payment from ConnDOT to avoid accrual of interest charges. The defendants' arguments that White Oak was not required to pay Steward's invoices until ConnDOT issued payment and accepted the work are not consistent with the language of the purchase order.10 Steward performed under the purchase order contract and fabricated, to varying extent, the four bid items. White Oak, however, repeatedly failed to make all of the required payments, in breach of the parties' contract.11 Sometimes White Oak made untimely payments; sometimes White Oak paid only part of the amount due under the invoices; eventually, White Oak ceased making any payments at all. Plaintiff's Exhibit 53, which is attached as Appendix A, summarizes the invoices issued, payments received, and running interest claimed by Steward. Insofar as the defendants argue that the purchase order required ConnDOT's inspection and approval before payment was due, see National Union Trial Brief at 51, the state inspector, who was present at Steward's plants during the fabrication, did approve Steward's work in advance of the invoicing. The calculation of Steward's damages for White Oak's breach of the purchase order contract is discussed below.

To the contrary, the terms of the purchase order provide that payment is not to be construed as acceptance or as conclusive evidence of satisfactory performance. Pl. Ex. 3 at 8, ¶ 10. National Union has argued that, by continuing to work on the Tomlinson Bridge project after declaring White Oak in default and threatening to discontinue manufacturing, Steward waived any breach. National Union Trial Brief at 26. "The general rule . . . is that a party for whose benefit a provision in a contract is intended may waive his rights under such provision." Loda v. H.K. Sargeant & Associates, Inc., 188 Conn. 69, 77 (1982). Waiver, a question for the finder of fact, "may be inferred from the circumstances if it is reasonable so to do." Id. at 76. Under the circumstances of this case, Steward's continued performance did not constitute a waiver of its right to enforce payment under the purchase order contract. -2611

10

Case 3:00-cv-00834-SRU 2.

Document 120

Filed 11/17/2006

Page 27 of 52

Relief Under Payment Bond for Payments Due Under Purchase Order

Pursuant to Conn. Gen. Stat. § 49-41, White Oak procured a payment bond, with National Union as surety, in the amount of its prime contract with the State: $87,868,378.10. Pl. Ex. 1 (dated June 6, 1994). Connecticut's Little Miller Act requires general contractors on public construction projects to obtain payment bonds for the protection of those providing labor and materials. Conn. Gen. Stat. §§ 49-41, 49-42, & 49-43. The Connecticut Supreme Court has described the statutory bond requirement as "designed to protect and benefit those who furnish materials and labor to the contractor on public work, in that they may be sure of payment of their just claims, without defeat or undue delay." American Masons' Supply Co. v. F.W. Brown Co., 174 Conn. 219, 227 (1974) (internal quotations marks and citation omitted). The "statutory provisions are to be liberally construed." Id. The Connecticut Supreme Court has concluded that the legislature intended the statute to operate in general conformity with the Miller Act and has considered, as precedent, decisions from federal courts based on the "apparent kinship between our own and the federal statutes of similar purpose." International Harvester Co. v. L.G. DeFelice & Son, Inc., 151 Conn. 325, 33233 (1964). See also, e.g., Blakeslee, 239 Conn. at 716 ("we have regularly consulted federal precedents to determine the proper scope of our statute"). The provisions of Conn. Gen. Stat. § 49-42 as in effect on June 6, 1994 govern this action. That section provided in pertinent part: (a) Every person who has furnished labor or material in the prosecution of the work provided for in [a contract for which] a payment bond is furnished under the provisions of section 49-41 and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which the claim is made, may enforce his right to payment under the bond by serving a notice of claim within one -27-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 28 of 52

hundred eighty days after the date on which he performed the last of the labor or furnished the last of the material for which the claim is made . . . . (b) . . . no [suit under this section] may be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied by the claimant. Conn. Gen. Stat. § 49-42 (1994).12 Thus, to recover payment under the bond, Steward must have filed a notice of claim within 180 days of the date when it last performed labor or furnished material. Conn. Gen. Stat. § 49-42(a) (1994). To be timely, Steward's lawsuit under section 4942 must have been commenced within one year from the date when it last performed labor or supplied material under the contract. Conn. Gen. Stat. § 49-42(b) (1994). Steward filed its notice of claim on December 20, 1999. That filing was timely under section 49-42(a) because Steward continued to perform labor or furnish material under the purchase order contract into 2000. In particular, Steward performed intermittent machining on pieces of the Tomlinson Bridge equipment. Steward's lawsuit, commenced approximately seven months later in July 2000, was timely under section 49-42(b). 3. Calculation of Damages for Breach of Purchase Order Contract a. Liability of White Oak

Because it breached its contract with the subcontractor, White Oak is liable for the unpaid balance and interest due under the purchase order contract. To the extent properly invoiced amounts were never paid, White Oak is liable to Steward for the amount of the unpaid balance plus interest at one percent per month under the terms of the purchase order contract. See West Haven Sound Development Corp. v. West Haven, 201 Conn. 305, 319 (1986) (noting that the

Section 49-42 was revised in October 1994. Citations to Conn. Gen. Stat. § 49-42 (1994) refer to the statute as of June 2004. -28-

12

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 29 of 52

general rule in breach of contract cases is that an award of damages should place the injured party in the same position it would have been absent the breach). Calculation of that amount, however, is problematic. During the project and after some invoices had been issued and paid, the parties reallocated the bid item prices, and invoices were adjusted to reflect that reallocation. As detailed above, Steward, the subcontractor, invoiced White Oak, the general contractor, and White Oak in turn invoiced ConnDOT, the project owner. Initially, Steward's invoices reflected the bid item values listed on the purchase order contract, including retainage of 2.5%.13 ConnDOT, however, issued payments to White Oak based on the value of the items according to the prime contract. In order to facilitate White Oak's collection of payment from ConnDOT, Steward and White Oak decided to adjust the bid amounts ­ though not the overall purchase order contract price. The adjusted contract prices mirrored the bid item values in White Oak's prime contract with ConnDOT. Three of the four individual items were priced higher in the prime contract than in the purchase order. For example, the most costly item, the counterweight sheaves, were initially invoiced at the purchase order value of $4.4 million, but after the reallocation, they were invoiced at the prime contract value of $5 million. White Oak and National Union have labeled this excess "overbilling." In other words, after the parties' reallocation, Steward billed White Oak based on the prime contract values, eventually charging White Oak amounts in excess of the bid items' prices in the purchase order contract. Although the parties agreed to the reallocation in an effort to collect more money from ConnDOT, Steward's invoices exceeded the contractual amounts on certain individual items. As a result, interest charges on the unpaid balances were also inflated.

Steward invoiced the entire amount due but immediate payment was not required for the 2.5% retainage. -29-

13

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 30 of 52

Plaintiff's Exhibit 53, Appendix A to this decision, summarizes the invoices submitted by Steward, White Oak's payments, and the running balance for principal and interest. From November 1994 to June 1996, the invoices were based on the purchase order values. During that period, Steward properly billed White Oak, and White Oak is liable for failing to timely pay those invoices (less retainage) in full. Starting on August 18, 1996, Steward began invoicing White Oak using the prime contract values. The change in pricing was an effort to "help White Oak get paid so [Steward Machine] could get paid." In addition, at some later date, a credit was issued against the principal balance in the amount of $338,529.74. It appears that the parties intended that sum to be credited against the principal balance as of November 15, 1996. Pl. Ex. 53. The credit was an attempt to adjust the amounts due based on the difference between the purchase order and the prime contract. It was not apparent from the evidence why Steward issued a credit in the amount of $338,529.74 when the difference between the two contracts was $367,000. Moreover, the credit did not account for interest that eventually accumulated based on the higher, prime contract values. Because Steward invoiced White Oak for the bid items at the prime contract values, its post-reallocation bills were inflated, sometimes reflecting amounts greater than the total value of the bid item under the purchase order. With respect to the post-reallocation invoices (i.e., those dating from August 18, 1996), it is necessary to calculate the amounts due by multiplying the bid item's purchase order value and the percentage complete. The attached Schedule A ("Purchase Order Contract - Revised Amounts Due"), included in Appendix B, shows the corrected amounts due following the reallocation. The amounts due are calculated based on the percentages complete and purchase order values. The schedule -30-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 31 of 52

indicates the revised totals, retainage, and amounts due. The attached Schedule B ("Purchase Order Contract - Revised Principal and Interest"), included in Appendix B, is styled on Plaintiff's Exhibit 53.14 The schedule incorporates the payments, payment dates, invoice numbers, and "days late" that were supplied by Steward.15 The revised amounts due are taken from Schedule A, and the calculations for interest are calculated based on those revised amounts.16 White Oak is liable to Steward for the unpaid balance and interest, calculated based on the values for the bid items in the parties' purchase order contract and Steward's completion percentages. In accordance with the parties' settlement agreement in the Replevin Action, contractual interest ­ a component of the plaintiff's damages ­ ceased accruing on August 24, 2000. Def. Ex. 565 at 9, ¶ 12. The sum of the total unpaid balance ($364,359) and contractual interest ($95,679) is: $460,038, and White Oak is liable for that amount. In addition, retainage is recoverable as a component of Steward's damages despite the parties' settlement agreement precluding recovery of damages "accruing" after August 24, 2000. The retainage accrued when Steward invoiced for the work completed under the purchase order contract even though payment for the 2.5% retainage was not due until White Oak accepted all

Plaintiff's Exhibit 53 is not helpfully organized, so deriving information from that schedule can be cumbersome. Nevertheless, I followed the format of Exhibit 53 when preparing Schedule B because Exhibit 53 accurately set forth the invoicing and payment history for the period prior to the reallocation. Three entries under the "days late" column were incorrect, based on the listed payment dates; those entries were corrected. The interest accrued was determined based on one-percent interest compounded monthly and the following formula: interest = P - (P/1.01n) where P is the principal and n is the number of months. -3116 15

14

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 32 of 52

goods under the purchase order or within 180 days of their final shipment. The machinery was shipped in 2000 and 2001, and retainage in the amount of $159,712 was due 180 days following the final shipment.17 White Oak is liable for that amount. b. Liability of National Union

Steward is entitled to enforce payment under the bond pursuant to Conn. Gen. Stat. § 4942. National Union, the surety that issued White Oak's payment bond, is liable to Steward for $619,750, the amount owed Steward under the purchase order contract for its work on the Tomlinson Bridge, including retainage and contractual interest at one-percent per month, through August 24, 2000. Conn. Gen. Stat. § 49-42 (1994) (in proceeding to enforce payment bond, court may allow interest at the rate of interested specified in the subcontract). B. Storage Fees 1. Collateral Storage Contract a. Liability of White Oak

Steward has argued that White Oak agreed to pay storage costs when the latter was unable to accept delivery of the Tomlinson Bridge machinery within the contracted delivery period. Steward has suggested that the agreement consisted of a collateral storage contract or, in the alternative, that the parties modified the purchase order, incorporating storage in addition to the manufacture and delivery of the machinery. The defendants contend that White Oak did not execute a separate storage contract and the purchase order's integration clause prevented its oral

Retainage of 2.5% is calculated based on the total amount due for the counterweight ropes ($947,210) and the revised total amounts due for the other three bid items, listed on the attached Schedule A: sheaves - $4,400,000; operating machinery - $826,200; lock machinery $215,050). Those amounts total $6,388,460. The retainage due equals $159,712, which is 2.5% of that total. -32-

17

Case 3:00-cv-00834-SRU modification.

Document 120

Filed 11/17/2006

Page 33 of 52

Steward's purchase order contained an integration clause and provided that the contract could not be modified unless in writing and signed by authorized representatives of Steward and White Oak. Pl. Ex. 3 at 7, ¶ 1. The parties' purchase order was not modified when Steward and White Oak agreed that Steward would store the machinery in exchange for additional payment. However, "nothing in the integration clause precluded the parties from forming an express agreement for additional services." Positive Impact Corp. v. Indotronix Intern. Corp., 96 Conn. App. 361, 365 (2006). "Whether a contractual commitment has been undertaken is ultimately a question of the intention of the parties." Otto Contracting Co. v. S. Schinella & Son, Inc., 179 Conn. 704, 709 (1980). The following evidence establishes that White Oak intended to undertake a contractual commitment to pay Steward in exchange for the subcontractor's storage and maintenance of the Tomlinson Bridge equipment. First, the evidence at trial showed that Steward resisted long-term storage of the Tomlinson Bridge machinery, and that Morrissey, White Oak's President, assured Steward that it would be compensated for storage. Second, in written correspondence, representatives of Steward, White Oak, and ConnDOT addressed storage options and agreed that the Tomlinson Bridge equipment would be stored and serviced at Steward's plants and that Steward would be compensated. See Pl. Exs. 14, 16, 18, 20; Def. Ex. 415. Third, their subsequent conduct was consistent with that agreement. Steward did not object to the invoices; rather, Steward forwarded them to ConnDOT for payment as it had forwarded invoices under the purchase order. Despite the absence of a formalized writing, White Oak and Steward did form a contract. In other words, there was a bargain between the two and a manifestation of mutual assent to the -33-

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 34 of 52

exchange. See Ubysz v. DiPietro, 185 Conn. 47, 51 (1981) (citing inter alia Restatement (Second), Contracts §§ 1(c), 15, 19 (Tent. Dr. 1964)). A party may manifest its assent to the exchange wholly or partly by written or spoken words or by other acts or by failure to act. Id. Here, White Oak manifested its assent to the storage agreement through: (1) Morrissey's spoken words to DeBardeleben, (2) written correspondence, in particular Hird's November 18, 1996 memorandum, Pl. Ex. 20, (3) White Oak's failure to object to the storage invoices, and (4) its forwarding of those invoices to the State. Steward proposed rates of $8 and $5 per square foot for indoor and outdoor storage, respectively, but the parties did not execute a written contract that contained a term regarding price. Pl. Exs. 19, 21. Although Steward and White Oak discussed the rates, there was no evidence of an explicit acceptance on the part of White Oak with respect to the amount of the storage charges. I find that in November 1996 Steward and White Oak agreed that Steward would store the Tomlinson Bridge equipment when the delays at the project site prevented delivery. The agreement to pay for storage was a separate contract, distinct from the purchase order contract. Def. Ex. 788 ("This storage issue is not a part of our [purchase order] contract with White Oak and should not affect our payments agreements [with White Oak and ConnDOT].").18 The

National Union has argued that entitlement for payment for storage was subject to ConnDOT's approval of Steward's storage invoices. National Union Trial Brief (doc. # 89) at 30. National Union cites a letter from Shivers, Steward's project manager, to Morrissey, in which Shivers asks White Oak to pursue past due invoices for storage with the State. Def. Ex. 788. National Union also points to a memorandum from Hird, White Oak's chief engineer, in which he notes that White Oak will forward Steward's storage invoices to ConnDOT "for their consideration." Def. Ex. 795. That evidence does not suggest that Steward contracted with ConnDOT to store the machinery. Rather, as under the purchase order contract, it suggests that Steward understood that White Oak would collect payment from ConnDOT for Steward's services. That arrangement does not negate White Oak and Steward's agreement regarding -34-

18

Case 3:00-cv-00834-SRU

Document 120

Filed 11/17/2006

Page 35 of 52

storage agreement contained no terms regarding payment or interest. Connecticut courts have held that "an agreement will not be rejected if the missing terms can be ascertained, either from its express terms or by fair implication." Presidential Capital Corp. v. Reale, 231 Conn. 500, 507-08 (1994). "[W]here the plaintiff and the defendant have agreed that the defendant will pay for the plaintiff's services but the agreement is silent as to the amount of compensation, the court may conclude that the defendant contemplated paying a reasonable fee." Id. at 508. Steward and White Oak contracted for the subcontractor to store the Tomlinson Bridge machinery when White Oak was unable to accept delivery. Steward and White Oak agreed that Steward's Birmingham plant was the only site where the machinery could be stored.