Free Description not available - District Court of Federal Claims - federal


File Size: 609.0 kB
Pages: 40
Date: September 10, 2008
File Format: PDF
State: federal
Category: District
Author: unknown
Word Count: 7,276 Words, 48,651 Characters
Page Size: Letter (8 1/2" x 11")
URL

https://www.findforms.com/pdf_files/cofc/99/83.pdf

Download Description not available - District Court of Federal Claims ( 609.0 kB)


Preview Description not available - District Court of Federal Claims
Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 1 of 24

No. 00-129C (Judge Allegra) IN THE UNITED STATES COURT OF FEDERAL CLAIMS ______________________________________________________________________________ LOCKHEED MARTIN CORPORATION, Plaintiff, v. THE UNITED STATES, Defendant.

DEFENDANT'S REPLY IN SUPPORT OF ITS CROSS-MOTION FOR SUMMARY JUDGMENT PETER D. KEISLER Assistant Attorney General DAVID M. COHEN Director OF COUNSEL: Gregory T. Allen Raymond J. M. Wong Defense Contract Management Agency DORIS S. FINNERMAN Trial Attorney Commercial Litigation Branch Civil Division Department of Justice Attn: Classification Unit 8th Floor 1100 L Street, N.W. Washington, D.C. 20530 Tele: (202) 307-0300 Fax: (202) 305-7643 Attorneys for Defendant

February 11, 2005

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 2 of 24

TABLE OF CONTENTS PAGE(S) I. II. Lockheed's Noncompliance With CAS 418 Did Not Result In Any Impact On Costs Paid By The Government Under Fixed-Price Contracts . . . . . . . . . . . . 2 Lockheed's Failure To Present A Claim To The Contracting Officer For Losses It Allegedly Incurred By Selling The CRAY Computers Prevents The Court From Possessing Jurisdiction To Entertain Lockheed's Claim . . . . . . . . . . . . . 8 A. B. C. II. Lockheed's Offset Claim Does Not Arise From The Same Set Of Operative Facts As Those Considered By The Contracting Officer . . . . . . . . . . . 9 The Government Has Had No Notice Of Lockheed's Claim . . . . . . . . . . . . . . . . 12 Lockheed's Loss May Not Be Allocable To Government Contracts . . . . . . . . . . 14

Mr. Blue's Affidavit May Not Be Considered By The Court . . . . . . . . . . . . . . . . . . . . . . 17

CONCLUSION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

i

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 3 of 24

TABLE OF AUTHORITIES CASES PAGE(S)

Applied Companies v. United States, 144 F.3d 1470 (Fed. Cir. 1998) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Attorney General v. Irish Northern Aid Committee, 530 F. Supp. 241 (S.D.N.Y. 1981) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Chen v. Mayflower Transit, Inc., 315 F. Supp. 2d 886 (N.D. Ill. 2004) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 Grenier v. Cyanamid Plastics, Inc., 70 F.3d 667 (1st Cir. 1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Kunz Const. Co. v. United States, 12 Cl. Ct. 74 (1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Larouche v. Webster, 175 F.R.D. 452 (S.D.N.Y. 1996) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 McKeown v. Sears Roebuck & Co., 335 F. Supp. 2d 917 (W.D. Wis. 2004) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 Midland Engineering Co. v. John A. Hall Construction Co., 398 F. Supp. 981 (N.D. Ind. 1975) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 PACCAR, Inc., ASPCA No. 27978, 89-2 B.C.A. § 21,696 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 Perry v. Martin Marietta Corp., 47 F.3d 1134 (Fed. Cir. 1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Santa Fe Engineers, Inc. v. United States, 818 F.2d 856 (Fed. Cir. 1987) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 In re Silverman Laces, Inc., 2002 WL 31412465 (S.D.N.Y. 2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

ii

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 4 of 24

Transamerica Premier Insurance Co. v. United States, 32 Fed. Cl. 308 (1994) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17, 18 Washington Central R.R. Co. v. National Mediation Board, 830 F. Supp. 1343 (E.D. Wis. 1993) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 FEDERAL STATUTES AND REGULATIONS 41 U.S.C. § 422 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2, 5, 10 48 C.F.R.§ 9903.201-3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8, 15 48 C.F.R. § 9903.201-4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 48 C.F.R. § 9903.306 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4, 6, 10 48 C.F.R. § 9904.418-40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Passim Fed. R. Evid. 801 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

iii

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 5 of 24

IN THE UNITED STATES COURT OF FEDERAL CLAIMS LOCKHEED MARTIN CORPORATION, Plaintiff, v. THE UNITED STATES, Defendant. ) ) ) ) ) ) ) ) No. 00-129C (Judge Allegra)

DEFENDANT'S REPLY IN SUPPORT OF ITS CROSS-MOTION FOR SUMMARY JUDGMENT Lockheed's complaint alleges that its "method of allocation of LITC's CRAY computer costs in calendar years 1994 and 1995 complies with the requirements of CAS 418 and CAS 403," and it requests the Court to find that its allocation method was in compliance with the CAS. See Complaint, Count I and Prayer For Relief. In our cross-motion for summary judgment, we demonstrated that Lockheed's allocation of its CRAY computer costs did not comply with CAS 418 because the allocation was based solely upon forecasts of usage without adjusting for actual usage of the computers by Lockheed's operating companies. Cross-motion at 10-17. In its opposition to our brief, Lockheed does not respond to this showing, and it does not offer any factual or legal basis to support its claim. Therefore, Lockheed has waived this claim.1 See Grenier v. Cyanamid Plastics, Inc., 70 F.3d 667, 678 (1st Cir. 1995) ("an issue raised in the Lockheed's conclusory allegation that it complied with CAS, Pl. Reply at 5-6, must be disregarded. Lockheed's only basis for this assertion is a conclusory remark by Mr. Blue that Lockheed complied with its Disclosure Statement. See Pl. App. 48, ¶¶ 7 and 8. This is clearly insufficient to prevent the Court from granting the Government's cross-motion for summary judgment. See Applied Companies v. United States, 144 F.3d 1470, 1475 (Fed. Cir. 1998) (conclusory statement in affidavit on ultimate issue does not create genuine issue of material fact sufficient to preclude summary judgment).
1

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 6 of 24

complaint but ignored at summary judgment may be deemed waived"); Chen v. Mayflower Transit, Inc., 315 F. Supp. 2d 886, 922 (N.D. Ill. 2004) ("Arguments not raised in opening briefs are waived"); McKeown v. Sears Roebuck & Co., 335 F. Supp. 2d 917, 939, 943 (W.D. Wis. 2004) (plaintiff waived claims by failing to respond to defendant's summary judgment motions or to develop an argument that would support his allegations). The Court should grant the Government's motion for summary judgment as to count I of the complaint. I. Lockheed's Noncompliance With CAS 418 Did Not Result In Any Impact On Costs Paid By The Government Under Fixed-Price Contracts When a contractor fails to comply with an applicable cost accounting standard, the contractor is liable for any increased costs, in the aggregate, which have been paid by the United States. 41 U.S.C. § 422. In our opening brief, we relied upon a document prepared by Lockheed to demonstrate that the effect of the noncompliance on cost-reimbursement contracts resulted in an overpayment by the Government of $540,000. Cross-Motion at 17. Lockheed does not dispute this cost effect. Pl. Reply at 6-7, n. 4. However, Lockheed contends that the Government's analysis of "increased costs in the aggregate" fails to include an alleged cost effect upon to Lockheed's fixed-price contracts.2 Lockheed's conclusion is incorrect; in this case, the effect on costs paid by the Government under fixed-price contracts is $0.

It is not entirely clear what amount Lockheed contends the Government underpaid on the fixed-price contracts. Lockheed alleges that even if its loss on the disposition of the CRAYs is disregarded, "the Government still underpaid Lockheed approximately $2.68 million of CRAY hourly computer costs allocable to government contracts." Pl. Reply at 6. Since the Government overpaid Lockheed by $540,000 for cost-reimbursable contracts, Lockheed presumably is alleging that the Government underpaid $3.22 million for the fixed-price contracts. Lockheed's current position is inconsistent with Lockheed's earlier contention that the Government underpaid $1.74 million for fixed-price contracts. See Def. App. 158. There is no evidentiary support for either figure. See section III, below. 2

2

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 7 of 24

When Lockheed estimated its costs for purposes of bidding on the fixed-price contracts in effect in 1994 and 1995 (the years of the noncompliance at issue in this case), its estimates were based upon the forecasts of usage made by the business segments.3 These "commitments" were then used to allocate the costs in 1994 and 1995, and Lockheed did not subsequently make any allocation adjustment to reflect actual usage of the CRAY computers by the business segments. This failure to allocate the costs associated with providing CRAY computer services to its business segments in proportion to the relative benefits received was not in compliance with CAS 418. See 48C.F.R. § 9904.418-40(c) ("Pooled costs shall be allocated to cost objectives in reasonable proportion to the beneficial or causal relationship of the pooled costs to cost objectives. . . . "); Perry v. Martin Marietta Corp., 47 F.3d 1134, 1137 (Fed. Cir. 1995) (Pursuant to CAS 418, cost pools are "allocated back to the segment base and their corresponding cost objectives (the CAS-covered contracts the segments are performing) in proportion to the relative benefits received on the basis of an established methodology"). Notwithstanding Lockheed's failure to make any adjustments in 1994 and 1995 to reflect actual usage, the estimates of usage used to determine fixed-price contracts would not have been any different even if Lockheed had

3

Lockheed's Disclosure Statement provided in part: Services provided to customers will be governed by service level agreements and documents of understanding. In these agreements customers commit to forecasts of resource usage. LITC plans on asset expenditures and support requirements based on assessments of workload requirements. Each company is billed for resources forecast by them, and allocated on their behalf.

Def. App. 3. Lockheed does not dispute our description of its estimating process; rather, it contends that such fact is irrelevant. Pl. Reply at 10. 3

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 8 of 24

used a compliant method for cost accumulation, that is, even if it used pre-established rates adjusted for actual costs. Since any adjustments for variances are generally made at the end of the accounting period, they do not affect the fixed-price contracts negotiated during the accounting period. The relevant regulatory provision applicable to fixed-price contracts is not subsection (e) of 48 C.F.R. § 9903.306, as Lockheed contends. Pl. Reply at 8. Rather, the relevant provision is subsection (b), which provides: If the contractor under any fixed-price contract, including a firm fixed-price contract, fails during contract performance to follow its cost accounting practices or to comply with applicable Cost Accounting Standards, increased costs are measured by the difference between the contract price agreed to and the contract price that would have been agreed to had the contractor proposed in accordance with the cost accounting practices used during contract performance. The determination of the contract price that would have been agreed to will be left to the contracting parties and will depend on the circumstances of each case. (emphasis added).4 Using this definition, Lockheed has not and cannot demonstrate that there is any difference between the contract price agreed to and the contract price that would have been agreed to. Lockheed does not contend that the estimates were inaccurate or misleading when they were made, nor does Lockheed contend that the estimates did not comply with the cost accounting standards. Therefore, even if Lockheed had subsequently made an adjustment in its

While the regulation cited by Lockheed, section 9903.306(e), permits an adjustment to the contract price for fixed-price contracts where appropriate, it does not logically follow that a noncompliance with CAS will always have a cost impact on fixed-price contracts. There is a cost impact if and only if there is a difference between the contract price agreed to and the contract price that would have been agreed to. 4

4

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 9 of 24

allocation based upon actual usage, its price proposals for fixed-price contracts would still have been based upon the best estimates of usage at that time. The following example demonstrates this analysis: Assume that the contractor enters into two contracts: Contract A, a firm, fixed-price contract, and Contract B, a cost-reimbursable contract. Each contract is for a period of one year. The contractor estimates, and the Government accepts, the following computer costs for each contract, based upon the commitments that the managers of Contract A and Contract B have made to the computer center. The commitments are based on the manager's best estimate of the computer hours each segment will require. Commitment for computer costs Contract A Contract B $75,000 $75,000

The contractor's practice is to accumulate the commitment amount, a practice that is not in compliance with CAS. The contractor does not adjust the accumulated costs to reflect the difference between the commitment and the actual amount. At the end of the contract the actual computer costs used by each contract is as follows: Actual computer costs Contract A Contract B $90,000 $60,000

The CAS statute states that the Government shall not pay more than the increased costs, in the aggregate, as defined by the CAS Board. 41 U.S.C. § 422(h)(3). The CAS Board has defined increased costs as follows: Increased costs are deemed to have resulted whenever the 5

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 10 of 24

cost paid by the Government is higher than it would have been had applicable cost accounting standards been complied with. 48 C.F.R. § 9903.306(a). For fixed-price contracts, the increased costs are measured by the difference between the contract price agreed to and the contract price that would have been agreed to. 48 C.F.R. § 9903.306(b), In accordance with these definitions, the increased costs for Contract A, which is a fixedprice contract, is $0. In this example, the contract price agreed to for Contract A was $75,000. In addition, the price that would have been agreed to for Contract A had the contractor used a compliant practice is also $75,000, even if the contractor used a compliant practice of adjusting the commitment costs to actual cost. This is because the original estimate of $75,000 was the best estimate available to both parties at the time of negotiations. Neither party would know at the time of negotiations if or how much the actual costs would ultimately differ from the estimate. Whether the CAS required an adjustment to actual costs was irrelevant at the time of estimating the contract costs. Thus, the difference between the contract price that was agreed to ($75,000) and the contract price that would have been agreed to ($75,000) is $0. The increased costs for Contract B is $15,000. As defined in section 9903.306(a), increased costs result whenever the cost paid by the Government is higher than it would have been had applicable cost accounting standards been complied with. Contract B is a costreimbursable contract. As such, the amount paid by the Government will equal the amount of accumulated costs. In this example, the cost paid by the Government will be $75,000 if the costs are accumulated using the noncompliant practice of using the commitment amount. However, the cost paid by the Government will be only $60,000 if the costs are accumulated using a

6

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 11 of 24

compliant practice of adjusting to actual costs. Therefore, the costs paid by the Government will be $15,000 higher than if a compliant practice had been used. To compute the increased costs in the aggregate, one must add the increased costs computed for fixed-price contracts, as defined by the CAS Board, and the increased costs computed for cost-reimbursable contracts, as defined by the CAS Board. In this example, the increased costs in the aggregate total $15,000 ($0 plus $15,000). To summarize, the actual costs accumulated under the contract are irrelevant for the fixed- price contract because under a fixed-price contract, the amount to be paid is fixed at the time the contract is negotiated. Thus, the contractor will receive $75,000 regardless of how much the actual computer costs are. However, for cost-reimbursable contracts, the actual costs accumulated are the basis for reimbursement of the costs. Thus, the noncompliance affects costreimbursable contracts; it does not impact fixed-price contracts. This example is the same as the facts in this case. The increased cost for the fixed-price contracts is $0. The amount of increased cost for the cost-reimbursable contracts is the increased costs in the aggregate. Lockheed's citation to a DCAA document that provides guidance on the determination of cost impact does not assist its position. Like the regulation cited by Lockheed, 48 C.F.R. § 9903.306(e), the guidance recognizes that fixed-price contracts may be relevant in determining cost impact. The guidance does not support Lockheed's conclusion that fixed-price contracts are relevant in all circumstances. As the guidance and the regulations make clear, a CAS noncompliance may occur in estimating costs and/or in accumulating costs. See, e.g., 48 C.F.R. § 9904.401-30 (defining 7

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 12 of 24

"accumulating costs" and "estimating costs"); 48 C.F.R.§ 9903.201-3 (requiring a contractor to certify that its practices used in estimating costs in pricing the proposal are consistent with the cost accounting practices disclosed in its Disclosure Statement); 48 C.F.R. § 9904.401-60 (providing illustrations of practices used in estimating costs and practices used in accumulating costs). Thus, the DCAA guidance states: "Estimating noncompliances affect primarily [fixedprice] contracts, while accumulation noncompliances affect only flexibly-priced contracts." Pl. App. 95 (emphasis added). In this case, there is no allegation that Lockheed's practices in estimating its costs were not in compliance with the CAS. See Pl. App. 26-27 (contracting officer's final decision). Rather, the issue here is Lockheed's accumulation noncompliance because the actual costs associated with the CRAYs were not properly allocated to the business segments which used these services. This accumulation noncompliance had a cost impact only upon costreimburseable contracts. II. Lockheed's Failure To Present A Claim To The Contracting Officer For Losses It Allegedly Incurred By Selling The CRAY Computers Prevents The Court From Possessing Jurisdiction To Entertain Lockheed's Claim In our opening brief, we demonstrated that the Court did not possess jurisdiction to consider two new claims asserted by Lockheed in its motion for summary judgment: (1) that Lockheed is entitled to allocate its costs associated with the sale of CRAY computers, which allocation should offset any cost impact resulting from an allocation of costs associated with the usage of the CRAY computers, and (2) that Lockheed is entitled to an equitable adjustment equal to the allocable portion of Lockheed's loss on the disposition of the CRAY computers. The latter claim has now been withdrawn by Lockheed. See Pl. Reply at 5. With respect to the first claim, 8

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 13 of 24

Lockheed asserts that it is seeking partial summary judgment as to entitlement only; Lockheed is unable to quantify "the precise amount" of the loss allegedly allocable to Government contracts. See Pl. Reply at 2, n. 1. A. Lockheed's Offset Claim Does Not Arise From The Same Set Of Operative Facts As Those Considered By The Contracting Officer

Lockheed does not deny that it never presented a claim to the contracting officer addressing the allocation of costs associated with the sale of the CRAY computers. Nor does Lockheed deny that this claim was not raised in its complaint, its reply to the Government's counterclaim, or the joint preliminary status report. See Def. Cross-Motion at 20. Rather, Lockheed simply makes the conclusory assertion that the claim arises from "the same set of operative facts" that were considered by the contracting officer. See Pl. Reply at 3, 11-12. The claim now asserted by Lockheed ­ that "Lockheed is entitled to charge government contracts the allocable portion of Lockheed's loss on the disposition of the CRAY computers," Pl. Reply at 1 ­ does not arise from the same set of operative facts that were considered by the contracting officer in making his final decision of March 16, 1999 (Pl. App. 26-27A). As reflected in the correspondence between Lockheed and the contracting officer, the relevant facts considered by the contracting officer were the annual commitments for usage of the CRAY computers agreed to by the business segments, the actual usage of CRAY computers by the business segments, and whether Lockheed's allocation of the actual costs based solely upon the commitments violated CAS 418. See Def. App. 34-47. With respect to Lockheed's new claim, the operative facts include Lockheed's Disclosure Statement setting forth its practice for treatment of gains and losses upon disposition of property,

9

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 14 of 24

the fact that Lockheed traded-in its two CRAYs for a new CRAY, its actual accounting practices for recording property sale transactions, its actual treatment of the gains and losses associated with the sale of the CRAYs, and whether Lockheed's allocation of the costs associated with such sale was in accordance with CAS 409, as Lockheed contends. See Pl. Motion at 12; Pl. Reply at 11 (arguing that Lockheed is entitled to charge the Government for these losses in accordance with 48 C.F.R. § 9904.409(b)(4)). The issue considered by the contracting officer was the allocation of costs incurred to provide CRAY computers for use by the business segments during the years 1994 and 1995. The issue presented by Lockheed's offset claim is the allocation of gains and losses upon the sale of the CRAY computers. These transactions did not occur at the same time nor was either transaction dependent upon the other. Because of the disparate nature of the accounting issues involved, they are addressed in separate sections of Lockheed's Disclosure Statement. See Def. App. 3-4 (addressing allocation of computer expenses); Def. App. 171-72 (addressing treatment of gains and losses on disposition of depreciable property). These different accounting issues are also addressed in different provisions of the cost accounting standards, CAS 418 and CAS 409. Nor does the CAS provide for an offset for unrelated allocation issues. The CAS statute, 41 U.S.C. § 422(h), requires the Government to recover "increased costs" resulting from a noncompliance, but it does not provide for an offset against a different noncompliance. Accordingly, the CAS Board has not promulgated any regulations that permit offsets for different noncompliances. See 48 C.F.R. § 9903.306. Thus, Lockheed's new claim is not simply an increase over the amount of the monetary claim that was before the contracting officer, as Lockheed suggests. In Santa Fe Engineers, Inc. 10

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 15 of 24

v. United States, 818 F.2d 856, 858-60 (Fed. Cir. 1987), the court rejected a similar argument. There, the contractor had submitted a claim to the contracting officer for increased costs resulting from three change orders. Upon appeal of the contracting officer's final decision, the contractor sought to recover an "impact" claim, arising from the collective nature of all the changes that were issued on the project. The court rejected the assertion that the contractor was merely increasing the amount of its claim. Rather, the court held that this latter claim was a new claim that had not been presented to contracting officer, and the court had no jurisdiction to entertain the claim. The circumstances are no different here. Moreover, even if Lockheed's new claim were nothing more than a change in the dollar amount of the claim, the Court would still lack jurisdiction. In Kunz Const. Co. v. United States, 12 Cl. Ct. 74, 79 (1987), the Court acknowledged that it could exercise jurisdiction over a claim the dollar amount of which was enlarged over the amount presented to the contracting officer if (1) the increase in the amount of the claim is based on the same set of operative facts previously presented to the contracting officer, and (2) the court finds that the contractor neither knew nor reasonably should have known, at the time when the claim was presented to the contracting officer, of the factors justifying an increase in the amount of the claim. Accordingly, the Court did not possess jurisdiction to consider the contractor's claim for home-office overhead, which was known to the contractor but not included in its claim to the contracting officer. In this case, the contracting officer issued his final decision on March 16, 1999. At that time, Lockheed should have known the costs associated with the disposition of the CRAYs in 1995. Lockheed tries to further avoid the requirement that it submit to the contracting officer a written demand seeking, as a matter of right, the payment of money in a "sum certain," see 11

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 16 of 24

Reflectone, Inc. v. Dalton, 60 F.3d 1572, (Fed. Cir. 1995), by contending that the Government has "available to [it] all the documentation necessary to calculate the amount of the underpayment." Pl. Reply at 15. Remarkably, Lockheed does not even identify the documents necessary for this calculation. This contention is also remarkable in light of Lockheed's admission that it is unable to quantify "the precise amount" of the loss allegedly allocable to Government contracts. See Pl. Reply at 2, n. 1.5 At bottom, Lockheed did not submit a claim to the contracting officer, and the claim, which has been presented here for the very first time, does not arise from the same set of operative facts presented to the contracting officer. The Court does not possess jurisdiction to entertain this claim. B. The Government Has Had No Notice Of Lockheed's Claim

Lockheed falsely claims that "facts concerning Lockheed's loss on the disposition of the CRAY computers have been produced in discovery." Pl. Reply at 12. Mr. Blue's declaration, cited by Lockheed, does not support that assertion. Mr. Blue merely avers that the issue was discussed at a meeting between the parties on April 11, 2002, and that the presentation by Lockheed "included information on this topic." Pl. App. 48, at ¶ 9. Notwithstanding five sets of interrogatories, four requests for production of documents, and a request for admissions propounded by the Government, Lockheed cannot identify a single discovery request relating to the sale of the CRAYs. The lack of discovery on this issue is apparent from the parties' dispute as to the date of the sale. In its opening motion, Lockheed Lockheed further fails to explain how it arrived at the conclusion that the disposition had a cost impact of $6.8 million, while it purportedly took write-offs totaling $7,442,615 (Pl. App. 69-72). 12
5

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 17 of 24

alleged that costs were properly allocable in 1995. Pl. Motion at 12. Lockheed, however, offered no evidence of that factual assertion. In our cross-motion, we demonstrated that Lockheed continued to use the CRAYs in 1996, which suggests that Lockheed did not dispose of the CRAYs in 1995. Cross-motion at 21, n. 5; Def. App. 40. In its reply, Lockheed asserted that the "record incontrovertibly shows that the CRAY computers were disposed of in December of 1995." Pl. Reply at 11. Finally, Lockheed provided an evidentiary basis for this allegation: two letter agreements dated December 22, 1995, between Lockheed and Cray Research providing for the sale by Lockheed and purchase by Cray of two CRAY computers, a leaseback by Lockheed of one of the CRAY computers, and a sale by Cray and purchase by Lockheed of a third, smaller CRAY computer. A third document, a letter from Cray, describes the transaction as a "trade-in." See Pl. App. 50-52. These documents were not provided to the Government during discovery (as demonstrated by the absence of a Bates number, which was added by Lockheed to all of the documents it produced during discovery). With respect to Mr. Blue's assertion that "information on this topic" was presented by Lockheed to the Government at a meeting on April 11, 2002, Mr. Blue refers to the single-page document, "Cost Impact Conclusion," prepared by Lockheed for settlement discussions, Def. App. 158. The document references the "1997 Corporate Reallocation/Write Down," which is an apparent reference to the alleged 1995 sale of the computers. At an earlier meeting between the parties, in March 2002, Lockheed also made a presentation. In that presentation, Lockheed set forth a calculation of increased costs in the aggregate, and it did not include any loss allegedly attributed to the sale of the CRAY computers. Nor did the presentation contain any mention of the sale of the CRAY computers. See Def. App. 173-83 (Lockheed's power point presentation). 13

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 18 of 24

Finally, with respect to Lockheed's allegation that the Government "audited" the Lockheed document entitled "Cost Impact Conclusion," Pl. Reply at 3-4, 17, Lockheed is misinformed. The DCAA did not conduct an audit of the document or of the loss resulting from the sale of the CRAYs. The DCAA did not review any documents relating to Lockheed's sale of the CRAY computers. Rather, in preparation for trial, DCAA was requested to provide expert advice concerning the correctness of Lockheed's methodology. This advice by the DCAA is not discoverable. See Rule 26(b)(4)(B). C. Lockheed's Loss May Not Be Allocable To Government Contracts

Presented for the very first time with a claim by Lockheed that it is entitled to allocate its costs associated with the sale of CRAY computers, we demonstrated in our cross-motion that, because it appeared that Lockheed was still using the CRAY computers in 1996, Lockheed's alleged loss incurred in 1996 had no relevance to increased costs paid by the Government in 1994 and 1995. Cross-motion at 21 n. 5. Notwithstanding this demonstration, Lockheed inexplicably contends that we are precluded from making any further arguments as to the merits of this claim. Pl. Reply at 2 and n.2. At the same time, Lockheed has produced ­ for the very first time ­ documents describing the details of the transaction. These documents reflect that Lockheed traded-in the two CRAYs for $170,000, in return for a CRAY, which it purchased for $200,000. Def. App. 50-52. Under these circumstances, any loss resulting from the sale of the CRAYs may not be allocated to Government contracts. The CAS regulations provide:

14

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 19 of 24

(j)(1) Gains and losses on disposition of tangible capital assets shall be considered as adjustments of depreciation costs previously recognized and shall be assigned to the cost accounting period in which disposition occurs except as provided in subparagraphs (j) (2) and (3) of this subsection. . . . (2) Gains and losses on the disposition of tangible capital assets shall not be recognized where: *** (ii) The asset is given in exchange as part of the purchase price of a similar asset and the gain or loss is included in computing the depreciable cost of the new asset. 48 C.F.R. § 9904.409-50. Thus, subsection (j)(2) appears to preclude Lockheed from recognizing a loss in this case. Further, Lockheed's Disclosure Statement states that upon disposition, the gain or loss is taken into consideration in the depreciation cost basis of the new items, where trade-in is involved." Def. App. 171. The December 29, 1995, letter from Cray Research, Inc. to Lockheed (Pl. App. 50) states: "Enclosed are duly-executed copies of subject letters covering the purchase of a Cray J916 with related software license and maintenance services, in conjunction with the trade-in of the Cray YNP8X S/M 1720 and the YMP-4C 6M1522." This letter clearly shows that the existing Cray computers were a trade-in for the new Cray computer. Thus, in accordance with Lockheed's disclosed practices, the loss on the old CRAY computers must be included in the price of the new computers. It cannot be allocated in 1995, as Lockheed has asked for in its claim. Furthermore, it would violate the CAS to permit Lockheed to allocate the loss as proposed since the allocation is inconsistent with its Disclosed Practices. 48 C.F.R. § 9903.2014 requires that, for each contract, "The practices disclosed for this contract shall be the same as the practices disclosed and applied on all other contracts for and which contain a Cost 15

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 20 of 24

Accounting Standards (CAS) clause." In order to comply with this provision, Lockheed must include the loss in the price of the new CRAY computer, as provided in its Disclosure Statement; it cannot record the loss for 1995. Even if Lockheed was permitted to deviate from its disclosed practices (which CAS does not permit), Lockheed's allocation claim still raises several unanswered questions. For example, did Lockheed include the two CRAYs in the purchase price of the new CRAY? Was the loss that Lockheed is now seeking included in computing the depreciable cost of the new CRAY? If the answer to either of those questions is yes, then not only is the claim inconsistent with Lockheed's disclosed practices, it also would represent a double-charge of its costs. Finally, even if Lockheed's proposed new allocation does comply with the CAS, there is no authority permitting Lockheed to make this retroactive change and to reallocate costs to Government contracts. In PACCAR, Inc., ASPCA No. 27978, 89-2 B.C.A. § 21,696, the Armed Services Board of Contract Appeals refused to permit a contractor to change its allocation method retroactively. The contractor retroactively changed a noncompliant allocation method in order to comply with the CAS, and the change increased the costs on Government contracts. Nevertheless, the board denied the contractor's claims under either the cost accounting standards clause of its contracts or for reformation, holding that the DCAA's reviews of the company's disclosure statement did not amount to a guarantee or commitment that all areas of noncompliance would be discovered. Thus, the contractor was precluded from making a retroactive change that increased the costs to the Government. For all of these reasons, the Court must decline to entertain Lockheed's claim relating to the sale of the CRAYs. 16

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 21 of 24

III.

Mr. Blue's Affidavit May Not Be Considered By The Court Only evidence that would be admissible at trial may be considered by the Court in

reviewing a motion for summary judgment. Rule 56(e); see also 10B Wright, Miller & Kane, Fed. Prac. & Proc. Civ. 3d § 2738. Contrary to the assertion by Lockheed, Pl. Br. at 18, Mr. Blue did not have "direct involvement in the transactions and events at issue" in this case. As Mr. Blue's supplemental declaration makes clear, his only involvement in this case has been to calculate damages. See Pl. App. 1-2, ¶¶ 1-3. Mr. Blue's declaration is based entirely upon his review of documents. The information obtained from these documents is hearsay. See Fed. R. Evid. 801(c) ("'Hearsay' is a statement, other than one made by the declarant while testifying at the trial or hearing, offered in evidence to prove the truth of the matter asserted"). While the documents may be excepted from the hearsay rule as business records, Lockheed has not made the required showing to demonstrate the application of the exception. See Rule 803(6); Washington Cent. R.R. Co. v. Nat' Mediation Bd., 830 F. Supp. 1343, 1353 (E.D. Wis. 1993) (under Rule 803(6), "the proponent bears the burden of establishing these foundational requirements through the testimony of the custodian," and striking declaration as inadmissible hearsay where foundation was not established). Indeed, Lockheed has not even disclosed the documents upon which Mr. Blue relied. Lockheed relies upon Transamerica Premier Ins. Co. v. United States, 32 Fed. Cl. 308, 312-13 (1994), as authority for its position that it is not required to disclose these records. In Transamerica, a subrogation case, the issue was whether the surety had actually made a payment under its payment bond. To address this issue, the surety submitted the affidavit of a bond claims specialist, Mr. Pettygrove, who was employed by the surety and who had personal responsibility 17

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 22 of 24

for the claims filed against the bond. In addition, the surety provided documentation demonstrating the payment. In holding that the affidavit was sufficient, the Court observed that "the primary source of Mr. Pettygrove's information was not the company's books and records but, rather, the affiant's own 'personal knowledge of claims and expenses incurred by Transamerica for contractual obligations payable to claimants on various bonds executed by Transamerica,' including the matter in issue here." 32 Fed. Cl. at 312 (emphasis in original and added). Unlike Transamerica, the only source of Mr. Blue's information is the company's books and records. Accordingly, Mr. Blue's affidavit consists entirely of inadmissible hearsay. See In re Silverman Laces, Inc., 2002 WL 31412465 (S.D.N.Y. 2002) (summary judgment affidavit insufficient where affiant was not involved in the underlying transactions and his statements were based solely upon review of documents and interviews of witnesses); Larouche v. Webster, 175 F.R.D. 452, 455 (S.D.N.Y. 1996) (striking portions of affidavit of FBI supervisor that were not based upon personal knowledge); Attorney General v. Irish Northern Aid Comm, 530 F. Supp. 241, 252 (S.D.N.Y. 1981) (disregarding documents constituting inadmissible hearsay and affiant's conclusory interpretations of documents). Lockheed's reliance upon the hearsay testimony of Mr. Blue runs afoul of other rules of evidence as well. Rules 1001 and 1002 require that, to prove the contents of a writing, the original writing or a duplicate is required. Rule 1006 permits the contents of voluminous writings to be summarized, but it requires that the documents, upon which the summary is based, be made available for examination. In short, Lockheed cannot avoid producing the documents upon which it relies by citing only to conclusory statements made by Mr. Blue. See Midland Eng'g Co. v. John A. Hall Constr. Co., 398 F. Supp. 981, 989 (N.D. Ind. 1975) (striking affidavit 18

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 23 of 24

where "best evidence" rule was violated by not producing the documents and affiant did not have personal knowledge of facts independent of the documents). The affidavit of Mr. Blue is hearsay and it must be disregarded by the Court. CONCLUSION For the foregoing reasons, defendant respectfully requests the Court to deny Lockheed's motion for summary judgment, grant defendant's cross-motion for summary judgment, and enter judgment in favor of the Government in the amount of $540,000 plus interest from March 16, 1999. Respectfully submitted, PETER D. KEISLER Assistant Attorney General s/ David M. Cohen DAVID M. COHEN Director

19

Case 1:00-cv-00129-FMA

Document 83

Filed 02/11/2005

Page 24 of 24

OF COUNSEL: Gregory T. Allen Raymond J. M. Wong Defense Contract Management Agency

s/ Doris S. Finnerman DORIS S. FINNERMAN Attorney Commercial Litigation Branch Civil Division Department of Justice Attn: Classification Unit 8th Floor 1100 L Street, N.W. Washington, D.C. 20530 Tel: (202) 307-0300 Fax: (202) 305-7643 Attorneys for Defendant

February 11, 2005

20

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 1 of 16

No. 00-129C (Judge Allegra)

IN THE UNITED STATES COL~T OF FEDERAL CLAIMS

LOCKHEED MARTIN CORPORATION, Plaintiff,
V.

THE UNITED STATES, Defendant.

APPENDIX TO DEFENDANT'S REPLY IN SUPPORTOF ITS CROSS-MOTION FOR SUMMARYJUDGMENT

PETER D. KEISLER Assistant AttomeyGeneral

DAVID M. COHEN Director OF COUNSEL: Grego~N Allen T. RaymondJ. M. Wong Defense Contract ManagementAgency DORIS S. FINNERMAN Trial Attorney CommercialLitigation Branch Civil Division Department Justice of Attn: Classification Unit 8th Floor 1100 L Street, N.W. Washington, D.C. 20530 Tete: (202) 307-0300 Fax: (202) 305-7643 Attorneys for Defendant

February 11, 2005

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 2 of 16

INDEX TO APPENDIX PAGE S~ Letter from A.M. DiPasquale to James Rose, dated April 1, 1994, w/excerpt from enclosed Disclosure Statement ................... LocldaeedPowerPoint Presentation, March 2002 ................................................................ 170

173

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 3 of 16

~-~Lockheed Corporation
,~500 Granada Park Boulevard Caiabasas, California 91399 April Mr. James Rose Defense Corporate Executive Defense Contract Management Lockheed Corporation 4500 Park Granada Boulevard Calabasas, CA 91399 Subject: i, 1994

District

West

Revised Lockheed Corporation Dated April I, 1994 Rose:

Disclosure

Statement

Dear

Mr.

Attached is a revised Disclosure Statement for Lockheed Corporation's home office. This supersedes the last version you received dated June 18, 1993. This statement incorporates the changes documented in our letter to you of October 8, 1993 and our subsequent conversation where you stated your wording preferences. In addition, ~i~e~<~d~d ~he description of LITC allocation methods for computing resources and made some minor wording changes in other sections to reflect recent developments. We would be happy to provide you with copies to facilitate the review of the document. of our redlined drafts

Sincerely,

A. M. DiPasquale, Corporate Director Government Finance Relations Enclosure cc: Richard Dodd,

170

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 4 of 16

94F19!0000]
COST ACCOUNTING STANDARDS BOARD CAPITALIZATION PRACTICES PART Y--DEPRECIATION AND of Rcnovfing Unit LOCKHEED CORPORATION

DISCLOSURE STATEMENT
REQ. UIRED BU PUBZIO LAW 91--879

Item Description 5.4.0 Treatment of Gains and Losses on Disposition of Depreciable Property. Gains and losses are: (Check the appropriate block(s) and if more than one is checked, explain on a continuation sheet.) A. [] Credited or charged currently to the same B, [] Takeninto consideration in the depreciation overhead or G&A pools to ~'tfich the decost basis of the new items, where trade-in preciation of ~he nssets was charged. is involved C. [] Not accounted for separately, but reD. [] Credited or charged to Other (3fiscellaneflected in the depreciation reserve account ous) Income and Expense accounts Z. [] Not applicable Y. [~ Other(s) (Describe on a continuation sheet.) 5.5.0 "Capitalization or Expensing of Specified Costs. (Check one bZock on each li~e to indicate your practices regarding capitaHzatlon or expenein9 of specified costs incurred in connection with capito2 assets. If the same specified cost is sometimes expensed and sometimes capitaZized, check both blocks and describe on a continuation sheet the circumstances wheneach methodi~ used.) Cost (a) Freight-in (b)Installation costs (c) Sales taxes (d) Excise taxes (e) Architect-engineer fees (f) Overhauls(e:x-traor~tinary repairs) (g) 3lajor modifications ov betterments 5.6.0 A. Expensed [] ~ [] [] [] [] [] E. Capitalized [] [] [] [] [] []

Criteria for Capitalization. (Enter (a) the minimum dollar amohntof expenditures for acquisition, ditlon, aZteration and improvement of deprecMble assets: capitalized, and (b) the minimumnumber expected life years of capltaHzedassets. Use ~eadin zeros for dollar amount,e.g., 0150for $150. If mare 9 than one dollar amount or nu~er applies, show the information for the majority of your dep~'eciab~e assets, and enumerateon a continuation sheet the dollar amountsand/or numbero] years for each category or subcategory of a~sets involved which differ from those for the majority of assets.) (a) ]~inimum dollar amotmt~Y~g)-] (b) Minimum life years

5.7.0

Group or Mass Purchase. Are group or mass purchases (initial complement) of similar items, which indiv]dually are less than the capitalization amountindicated above, capitalized? (0heck one.)

k. [] Yes

B. [] No

171
FOI~£ C/SB-DS-t -16-

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/200594F19100001 16 Page 5 of CONTINUATION SHEET
qame of Reporting U~h Page 1 of 1 Page LOCKHEEDCORPORATION

COST ACCOUNTING STANDARDS BOARD DISCLOSURE STATEMENT REQUIRED PUBLIC LAW 91-379 BY
Item

Item Description 5.1.0 Depreciating Tangible Assets (d) Leasehold Improvements Useful life code - Leasehold improvements depreciated over the estimated life of the asset or the are remainingterm of lease (firm lease period excluding options}, whicheveris shorter. When the lease is for an indefinite term, the leaseholdimprovement depreciatedover the period of its estimated is life and upontermination of the lease, any unamortized balanceis written off.

(i)

Programming/reprogramming costs Internally developed software is expensed costs are incurred. as Individual pieces of purchasedsoftware are expensed cost is less than $1,000. However,software if purchasedas part of an original complement costing morethan $1,000 is capitalized.

Licensedsoftware with a unit cost of $6,000 or moreis capitalized.

5.4.0

Treatment of Gains and Losseson Disposition of Depreciable Property. Net gains and losses are recordedin the home office residual pool.

FORMCASB-DS-1

172

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 6 of 16

173

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 7 of 16

174

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 8 of 16

@

175

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 9 of 16

176

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 10 of 16

177

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 11 of 16

178

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 12 of 16

179

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 13 of 16

¯

¯

¯

@

@

¯

180

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 14 of 16

181

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 15 of 16

182

Case 1:00-cv-00129-FMA

Document 83-2

Filed 02/11/2005

Page 16 of 16

183