Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 1 of 32

San Jose Job Corps Center · Evaluation of Brero's Delay Analysis · Evaluation of Brero's Inefficiency Analysis

Slide 1

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 2 of 32

San Jose Job Corps Center
Brero Analysis
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days
4

Substantial Completion

8

Total Delay 162 days

Actual Construction ­ 652 days
17

Completion

162 days Compensable

LEGEND
Projected As-Built Delay

Slide 2

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 3 of 32

San Jose Job Corps Center
Brero Analysis ­ Corrections
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days
4

Substantial Completion

8

Total Delay 162 days

Actual Construction ­ 652 days
17

Completion

1.

Actual Substantial Completion October 18, 2004

162 days Compensable

LEGEND
Projected As-Built Delay

Slide 3

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 4 of 32

San Jose Job Corps Center
Brero Analysis ­ Corrections
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days
4

Substantial Completion

8

Total Delay 132 days

Actual Construction ­ 622 days
18

Actual Substantial Completion

1.

Actual Substantial Completion October 18, 2004

132 days Compensable

LEGEND
Projected As-Built Delay

Slide 4

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 5 of 32

San Jose Job Corps Center

Slide 5

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 6 of 32

San Jose Job Corps Center

Slide 6

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 7 of 32

San Jose Job Corps Center

Slide 7

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 8 of 32

San Jose Job Corps Center
Brero Analysis ­ Corrections
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days
4

Substantial Completion

8

Total Delay 132 days

Actual Construction ­ 622 days
18

Actual Substantial Completion

1. 2.

Actual Substantial Completion October 18, 2004. Time Extensions to September 9, 2004.

132 days Compensable

LEGEND
Projected As-Built Delay

Slide 8

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 9 of 32

San Jose Job Corps Center
Brero Analysis ­ Corrections
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days + 1+ 90 + 2
4

Substantial Completion

9

Actual Construction ­ 622 days
18

Actual Substantial Completion

1. 2.

Actual Substantial Completion October 18, 2004. Time Extensions to September 9, 2004.

132 days Compensable

LEGEND
Projected As-Built Delay

Slide 9

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 10 of 32

San Jose Job Corps Center
Brero Analysis ­ Corrections
J F M A M J J A S O

1993
N

D

J

F

M

A

M

J

J

A

S

O

1994
N

Notice to Proceed Contract Term - 490 days + 1+ 90 + 2
4

Substantial Completion

9

Total Delay 39 days

Actual Construction ­ 622 days
18

Actual Substantial Completion

1. 2.

Actual Substantial Completion October 18, 2004. Time Extensions to September 9, 2004.

39 days Compensable

LEGEND
Projected As-Built Delay

Slide 10

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 11 of 32

San Jose Job Corps Center

Slide 11

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 12 of 32

San Jose Job Corps Center

Slide 12

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 13 of 32

San Jose Job Corps Center

Slide 13

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 14 of 32

San Jose Job Corps Center · Contract Modification # 8 extended time of performance to September 9, 1994 (substantial completion). · Substantial Completion was achieved on October 18, 1994. · Therefore. delay period under consideration is from September 9, 1994 to October 18, 1994, or 39 days.

Slide 14

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 15 of 32

San Jose Job Corps Center · According to Brero's TIA, delays from September 9 to October 18, 1994 resulted from the following:
- COP 192 ­ Provide 6x8 concrete walk (1 day ­ September 9 to September 10, 1994) - Contractor extended performance of contract work ­ inexcusable (19 days ­ September 10 to September 29, 1994) - COP 209 ­ Additional Soil Amendment (1 day ­ September 29 to October 8, 1994) - COP 234 ­ Screens over wall louvers (10 days ­ October 8 to October 18, 1994)

Slide 15

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 16 of 32

San Jose Job Corps Center - Mod. 11

Slide 16

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 17 of 32

San Jose Job Corps Center ­ Mod. 11

Slide 17

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 18 of 32

San Jose Job Corps Center ­ Mod. 11

Slide 18

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 19 of 32

San Jose Job Corps Center · According to Brero's TIA, delays from September 9 to October 18, 1994, 39 days are inexcusable. Therefore, Brero is not entitled to any extended performance costs. · According to the Contract, Brero is subject to liquidated damages in the amount of $9,165 (39 x $235).

Slide 19

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 20 of 32

San Jose Job Corps Center ­ Liquidated Damages

Slide 20

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 21 of 32

San Jose Job Corps Center ­ Liquidated Damages

Slide 21

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 22 of 32

San Jose Job Corps Center

Slide 22

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 23 of 32

San Jose Job Corps Center ­ Brero's LOP Analysis

Slide 23

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 24 of 32

San Jose Job Corps Center ­ Brero's LOP Analysis
Months with no framing fragnets

Total LOP Hrs w/no Impacts

7411.56
Slide 24

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 25 of 32

San Jose Job Corps Center ­ Brero's LOP Analysis
Examples of Inefficiencies with no framing fragnets

61%

N had no fragnets

97%

M had no fragnets
Slide 25

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 26 of 32

San Jose Job Corps Center ­ Brero's LOP Analysis
Examples of Inefficiencies with no framing fragnets
September 1993

85%
February 1994

F had no fragnets

64%

H had no fragnets
Slide 26

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 27 of 32

San Jose Job Corps Center ­ Empirical Resource Curves ­ used in lieu of actual units installed

Slide 27

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 28 of 32

San Jose Job Corps Center ­ Certified Payrolls and Job Cost Report

Slide 28

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 29 of 32

San Jose Job Corps Center ­ Certified Payrolls and Job Cost Report

Slide 29

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 30 of 32

San Jose Job Corps Center ­ Certified Payrolls and Job Cost Report

Slide 30

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 31 of 32

San Jose Job Corps Center ­ Inefficiency During Roof Framing
February 1994

73%

76%
Slide 31

Case 1:00-cv-00775-TCW

Document 57-3

Filed 04/28/2006

Page 32 of 32

San Jose Job Corps Center ­ Inefficiency During Roof Framing

March 1994

69%

Slide 32